SECTION 00948 - Work Change Directive <br />No. 06 <br />DATE OF ISSUANCE: 6/15/16 EFFECTIVE DATE: 6/15/16 <br />OWNER: Indian River County <br />CONTRACTOR: Sunshine Land Design, Inc. <br />Project: Gifford Neighborhood 45"' Street Beautification Project <br />OWNER's Project No. 1506 <br />OWNER'S Bid No. 2015040 <br />You are directed to proceed promptly with the following changes: <br />Description: <br />Modification to existing pavement cross slopes (existing condition) to facilitate drainage from <br />the roadway at the 281' Court side street connection to 45th Street. <br />Purpose of Work -Change Directive: <br />Mitigate an existing pavement drainage condition and harmonize the existing project with <br />the right-of-way limits and connecting existing roadways. The existing crown configuration <br />along with adjacent right-of-way conditions at 28TM Court would have prevented sheet flow <br />from the roadway creating ponding and a subsequent maintenance condition. This required <br />additional profile milling to ensure adequate drainage could be established. <br />Attachments: (List documents supporting change) <br />Sunshine Land Design Proposal #09 <br />If OWNER or CONTRACTOR believe that the above change has affected Contract Price any <br />Claim for a Change Order based thereon will involve one or more of the following methods as <br />defined in the Contract Documents. <br />Method of determining change in <br />Contract Prices <br />0 Unit Prices <br />IR Lump Sum <br />0 Other. <br />0 By Change Order: <br />Method of determining change in <br />Contract Times <br />❑ Contractor's Records <br />E] Engineer's Records <br />0 Other:0-days, no impact to schedule <br />II By Change Order. <br />Estimated increase (decrease) of this Work Estimated increase (decrease) in Contract Times: <br />Change Directive <br />$1.290.00 Substantial Completion: 0 days; <br />If the change Involves an increase, the estimated <br />amount is not to be exceeded without further <br />authorization. <br />Ready for Final Completion:.0 days. <br />If the change involves an increase, the estimated <br />time is not to be exceeded without Further <br />authorization. <br />ACCE TED: <br />RECOMMENDED: <br />APPROVED: <br />By. <br />By: Z <br />By: <br />CONTRACTOR (Si ature) <br />ENG ER (Signatur <br />OWNER Signatu ) <br />Date: 1(e I tQ <br />Date: S t 4 <br />Date: 6 Z Z G 6 <br />RNPublic Works\ENGINEERING DIVISION PROJECTS11506-Gifford Neighborhood 45th St Beauti icatlon%Admin\Work Change <br />DirectivesMCD-06 28th Ct road profliing\IRC-1506 WCD-06_Roadway Grading 28th Ct.doo <br />P51 <br />