pay OWNER $ 1,148 for each calendar day that expires after the time specified in paragraph 3 02 <br /> for completion and readiness for final payment until the Work is completed and ready for final <br /> payment <br /> ARTICLE 4-CONTRACT PRICE <br /> 401 OWNER shall pay CONTRACTOR for completion of the Work an amount in current funds equal to <br /> the sum of the amounts determined pursuant to paragraph 4 01.A and summarized in paragraph <br /> 4 01.B, below <br /> A. For all Work, at the prices stated in CONTRACTOR's Bid, attached hereto as an exhibit <br /> B THE CONTRACT SUM subject to additions and deductions provided in the Contract Documents. <br /> Numerical Amount- $1,246,000.00 <br /> Written Amount: one million, two hundred forty-six thousand dollars <br /> ARTICLES -PAYMENT PROCEDURES <br /> 5.01 Progress Payments <br /> A. The OWNER shall make progress payments to the CONTRACTOR on the basis of the <br /> approved partial payment request as recommended by CONSULTANT in accordance with <br /> the provisions of the Local Government Prompt Payment Act, Florida Statutes section 218 70 <br /> et. seq. The OWNER shall retain ten percent (10%) of the payment amounts due to the <br /> CONTRACTOR until fifty percent (50%) completion of the work. After fifty percent (50%) <br /> completion of the work is attained as certified to OWNER by CONSULTANT in writing, <br /> OWNER shall retain five percent (5%) of the payment amount due to CONTRACTOR until <br /> final completion and acceptance of all work to be performed by CONTRACTOR under the <br /> Contract Documents. Pursuant to Florida Statutes section 218 735(8)(b), fifty percent(50%) <br /> completion means the point at which the County as OWNER has expended fifty percent <br /> (50%) of the total cost of the construction services work purchased under the Bid and <br /> Specification Documents, together with all costs associated with existing change orders and <br /> other additions or modifications to the construction services work provided under the <br /> Contract Documents. <br /> 502 Pay Requests <br /> A Each request for a progress payment shall contain the CONTRACTOR'S certification All <br /> progress payments will be on the bass of progress of the work measured by the schedule <br /> of values established, or in the case of unit price work based on the number of units <br /> completed After fifty percent (50%)completion,and pursuant to Florida Statutes section <br /> 218 735(8)(d), the CONTRACTOR may submit a pay request to the County as OWNER for <br /> up to one half (1/2) of the retainage held by the County as OWNER, and the County as <br /> OWNER shall promptly make payment to the CONTRACTOR unless such amounts are the <br /> subject of a good faith dispute, the subject of a claim pursuant to Florida Statutes section <br /> 255 05(2005), or otherwise the subject of a claim or demand by the County as OWNER or <br /> Page 2 of 7 <br />