Laserfiche WebLink
TABLE 7 <br />PROGRAM COST ESTIMATE <br />FOR REGIONAL SLUDGE FACILITY (1) <br />Item Estimated Cost <br />Total Construction Bid Amount (2): $4,600,000 <br />I <br />Construction Contingency (3) $ 460.000 <br />r <br />Estimated Engineering Costs (4): <br />( Design $ 286.000 <br />Special Services 39,000 <br />Bidding Services 25,000 <br />General Services 112,000 <br />Resident Services 255,000 <br />' Start-up Services 81,000 <br />r <br />Total Estimated Engineering Costs <br />Total Estimated Program Costs <br />$ 798,000 <br />$5,858,000 <br />(1) Does not include an estimated $ 120.000 of County administrative costs to <br />be defrayed from funds on hand. <br />(2) Taken from apparent low bid for the project. <br />(3) Equals 10 percent of Total Construction Bid Amount. <br />(4) Taken from page 6 of the July 3, 1989 Cost Recovery Report. <br />M.VRB2/8 <br />27 <br />