SECTION 00948 - Work Change Directive No. 01 <br />DATE OF ISSUANCE: January 18, 2016 EFFECTIVE DATE: January 18, 2016 <br />OWNER: Indian River County <br />CONTRACTOR: Kerns Construction & Property Management Corporation <br />Project: 87th Street and 911 Avenue Sidewalk Improvements <br />OWNER's Project No. 1205 <br />OWNER's Contract No. 2015036 <br />You are directed to proceed promptly with the following changes: <br />Description: <br />Revisions to the drainage improvements on 87th Street due to the existing drainage pattern. <br />The relocation of the sidewalk from the north side of 87th Street to the south side from station <br />82+00 to 98+00. Revisions to the drainage quantities and the addition of several quantity line <br />items. <br />Purpose of Work Change Directive: <br />To address the existing drainage pattern on 87th Street that was not accounted for with the <br />original design. <br />Attachments: (List documents supporting change) <br />Revised plans for 87th Street (Sheets 6 through 13 and 19 through 33) dated 1/14/16 <br />Revised Itemized Bid Schedule dated 1/18/16 <br />If OWNER or CONTRACTOR believe that the above change has affected Contract Price any <br />Claim for a Change Order based thereon will involve one or more of the following methods as <br />defined in the Contract Documents. <br />Method of determining change in <br />Contract Prices <br />X Unit Prices <br />❑ Lump Sum <br />❑ Other: <br />II By Change Order: <br />Method of determining change in <br />Contract Times <br />❑ Contractor's Records <br />❑ Engineer's Records <br />X_Other: Material Acquisition for Drainage Inlets <br />II By Change Order: <br />Estimated increase (decrease) of this Work Estimated increase (decrease) in Contract Times: <br />Change Directive <br />$23.301.30 Substantial Completion: 35 additional days; 4/27/16 <br />If the change involves an increase, the estimated <br />amount is not to be exceeded without further <br />authorization. <br />Ready for Final Completion. 5/27/16 <br />If the change involves an increase, the estimated <br />time is not to be exceeded without further <br />authorization. <br />ACCEPTED: <br />By: <br />RECOMMENDED: <br />By: <br />ENGINEER (Signature) <br />APP774 <br />By: <br />CONTRACTOR (Signatuure) <br />-OWNER (Signature) <br />Date: I I Int 20l <br />Date: / �g 1-6 <br />Date: a 6 <br />FAPublic WorksIENGINEERING DIVISION PROJECTS\1205-Vero Lake Estates Swk-87th St 101st Ave to CR510 (LAP)\Design\Work <br />Change Directives\WCD #1\00948 -Work Change Directive Rev 06-2013.doc <br />P106 <br />