SCOPE OF SERVICES <br /> Consultant will perform the following amended task services: <br /> TASK 1.0 COORDINATION WITH SJRWMD <br /> Subtask 1.1 Pre-Application Conference <br /> No change to this subtask. <br /> Subtask 1.2 Preparation of Modeling Approach Memorandum <br /> No change to this subtask. <br /> Subtask 1.3 Preparation of Permit Application <br /> In addition to preparing SJRWMD Form No.40C-2.900(1)(e),Consumptive Use Permit for Public Supply— <br /> Form E and supporting documentation as outlined in the original Scope of Services,the Consultant <br /> prepared the updated population projections and corresponding wellfield allocation for use in <br /> determining the modeling scenarios to be used. Best available information provided by the County was <br /> in the form of ERUs in use, reserved,or newly sold (including projections).This is not a conventional <br /> method of demonstrating population and demand for CUP purposes; however,SJRWMD staff <br /> recognized that the County is in a unique position due to the large volume of reserve capacity(ERUs that <br /> have been purchased for units that have not yet been constructed)and agreed to accept the <br /> methodology.Several iterations of the demand tables were prepared and numerous meetings were held <br /> with SJRWMD and County staff to finalize the demand numbers to be used in the modification request. <br /> This amended subtask includes 9 iterations of the tables and 11 meetings/conference calls to finalize the <br /> demand projections. <br /> In addition,Consultant assisted with coordination and updates to the previous avoidance plan action <br /> items to address the items that were not completed in accordance with the approved schedule.This was <br /> not included in the original Scope of Services(only the update to the avoidance plan resulting from the <br /> current modeling effort was included). <br /> Subtask 1.4 Response to Requests for Additional Information <br /> No change to this subtask. <br /> Subtask 1.5 Review of Draft Permit <br /> No change to this subtask. <br /> Task 2.0 MEETING WITH SJRWMD <br /> No change to this subtask. <br /> TASK 3.0 PROJECT MANAGEMENT AND QUALITY CONTROL <br /> Activities performed under this task consist of those general functions required to maintain the project <br /> on schedule,within budget,and that the quality of the work products defined within this scope is <br /> consistent with Consultant's standards and the County's expectations.Specific activities included are <br /> identified below: <br /> • Subtask 3.1 Project Quality Management <br /> No change to this subtask. <br /> Subtask 3.2 Project Status Reports <br /> No change to this subtask. <br /> 1,2036_Etr with Exhiblts.docx A-2 ga <br />