Work Order No. 2 <br />43rd Avenue & 261h Street <br />Intersection Improvements <br />EXHIBIT C—TIME SCHEDULE <br />Upon authorization to proceed by the COUNTY, final design documents are expected <br />to take approximately nine (9) months from the Notice to Proceed (NTP). <br />Initial Submittal (40% Design Drawings) <br />Interim Submittal (80% Design Drawings) <br />Final Submittal (100% Design Drawings) <br />contingent upon BOCC approval <br />3 months following.NTP <br />7 months following NTP <br />9 months following NTP <br />(THE REMAINDER OF THIS PAGE IS INTENTIONALLY BLANK) <br />Page 7 of 8 <br />