in the Project ornot, will pass to OWNER nolater than <br />the time of payment free and clear of all Liens. <br />14.04 Substantial Completion <br />A. When CONTRACTOR considers the entire <br />Work ready for its intended use CONTRACTOR shall <br />notify OWNER and ENGINEER in writing that the <br />entire Work kusubstantially complete (except for items <br />specifically listed by CONTRACTOR as incomplete) <br />and request that ENGINEER issue a certificate of <br />Substantial Completion. PnonmmOv thereafter, <br />OWNER, CONTRACTOR. and ENGINEER mheU <br />nneka on inspection of the \8kzrk to determine the <br />status ofcompletion. |fENGINEER does not consider <br />the Work substantially oornp|ate. ENGINEER will <br />notify CONTRACTOR in vvhdng giving the reasons <br />therefore. if ENGINEER GensideFs the VV9Fk <br />. <br />B. OWNER shall have the right to exclude <br />CONTRACTOR from the Site after the date of <br />Substantial Completion, but OWNER shall allow CON- <br />TRACTOR reasonable mcoaas to complete or correct <br />items onthe tentative list <br />14.05 Partial Utilization <br />A. Use bvOWNER adOWNER'soption of any <br />substantially completed part ofthe Work which has <br />specifically been identified inthe Contract Documents, <br />orwhich OWNER, ENGINEER, and CONTRACTOR <br />agree constitutes aseparately functioning and usable <br />part of the Work that can be used by OWNER for its <br />intended purpose without significant interference with <br />C(]NTRACTOF1's performance of the remainder of <br />the Work, may be accomplished prior to Substantial <br />Completion of all the Work subject to the following <br />conditions. <br />1. OWNER at any time may request <br />CONTRACTOR in writing to permit OWNER to <br />use any such part ofthe Work which OWNER <br />believes to be ready for its intended use and <br />substantially complete. If CONTRACTOR <br />agrees that such part of the Work is <br />substantially oomnp|eba. CONTRACTOR Will <br />certify to OWNER and ENGINEER that such <br />port of the Work is substantially complete and <br />request ENGINEER to issue a certificate of <br />Substantial Completion for that pod of the <br />Work. CONTRACTOR otany time may notify <br />OWNER and ENGINEER in writing that <br />CONTRACTOR considers any such part ofthe <br />Work ready for its intended use and nubston- <br />tio|hcomplete and request ENGINEER to issue <br />o certificate of Substantial Completion for that <br />part of the Work. Within e reasonable time <br />after either such request, OVVNER. <br />CONTRACTOR, and ENGINEER shall make <br />an inspection of that part of the Work to <br />determine its abubus of completion. if <br />ENGINEER does not consider that part ofthe <br />Work tobesubstantially complete, ENGINEER <br />will notify OWNER and CONTRACTOR in <br />writing giving the reasons therefor. if <br />ENGINEER considers that part ofthe Work bo <br />be substantially oonmp|ebn. the provisions of <br />paragraph 14.04 will apply With respect to <br />certification of Substantial Completion of that <br />part of the Work and the division of <br />responsibility in respect thereof and ecoeoa <br />thereto. <br />2 Nooccupancy orseparate operation <br />prior <br />of part of the Work may occur <br />00700 - General Conditions REV 5-10-13 <br />00mu-m <br />mpublicvmowswamsenwoommmwpnoJEonax05-oncunesurfmoopU"wmm125thmwmmiffm m="e^mMa*erc**a,00c"me"ts\00700'General Conditions <br />