Laserfiche WebLink
SC-13.05 OWNER May Stop the Work <br /> SC-13.05.A. Delete paragraph GC-13.05.A in its entirety and insert the following paragraph in its <br /> place: <br /> A. If the Work is defective, or CONTRACTOR fails to supply sufficient skilled <br /> workers or suitable materials or equipment, or fails to comply with permit <br /> requirements, or fails to comply with the technical specifications, or fails to <br /> perform the Work in such a way that the completed Work will conform to the <br /> Contract Documents, OWNER may order CONTRACTOR to stop the Work, or any <br /> portion thereof, until the cause for such order has been eliminated; however, this <br /> right of OWNER to stop the Work shall not give rise to any duty on the part of <br /> OWNER to exercise this right for the benefit of CONTRACTOR, any <br /> Subcontractor, any Supplier, any other individual or entity, or any surety for, or <br /> employee or agent of any of them. <br /> SC-13.07 Correction Period <br /> SC-13.07 A. Delete the first sentence of paragraph GC-13.07.A in its entirety and insert the <br /> following sentence in its place <br /> A. If within one year after the date of Final Completion or such longer period of time <br /> as may be prescribed by Laws or Regulations or by the terms of any applicable <br /> special guarantee required by the Contract Documents or by any specific provision <br /> of the Contract Documents, any Work is found to be defective, or if the repair of <br /> any damages to the land or areas made available for CONTRACTOR's use by <br /> OWNER or permitted by Laws and Regulations as contemplated in paragraph <br /> 6.11.A is found to be defective, CONTRACTOR shall promptly, without cost to <br /> OWNER and in accordance with OWNER's written instructions: (i) repair such <br /> defective land or areas, or(ii) correct such defective Work or, if the defective Work <br /> has been rejected by OWNER, remove it from the Project and replace it with Work <br /> that is not defective, and (iii) satisfactorily correct or repair or remove and replace <br /> any damage to other Work, to the work of others or other land or areas resulting <br /> therefrom. <br /> SC-13.07 B. Delete paragraph GC-13.07.8 in its entirety and insert the following sentence in its <br /> place <br /> B. In special circumstances where a particular item of equipment is placed in continu- <br /> ous service before Final Completion of all the Work, the correction period for that <br /> item may start to run from an earlier date if so provided in the Specifications or by <br /> Written Amendment. <br /> SC-14.02 Progress Payments <br /> SC-14.02.6.5. Delete paragraph GC-14.02.8.5.d in its entirety and insert the following paragraph <br /> in its place: <br /> d. ENGINEER has actual knowledge of the occurrence of any of the events <br /> enumerated in paragraph 15.02.A; or <br /> SC-14.02.6.5. Add the following sentences at the end of paragraph GC-14.02.8.5: <br /> 00800-8 <br /> 00800-Supplementary Conditions 05-13 rev <br /> 00800 8F:\Public Works\ENGINEERING DIVISION PROJECTS\1765 Sebastian Corners Roof Replacement\1-Admin\Bid DocumentsWlaster Contract DocumentsWlaster <br /> Contract Documents\00800-Supplementary Conditions 05-13 rev.doc <br />