in the Projector not, will pass to OWNER no later than <br />the time of payment free and clear of all Liens. <br />14.04 Substantial Completion <br />A. When CONTRACTOR considers the entire <br />Work ready for its intended use CONTRACTOR shall <br />notify. OWNER and ENGINEER in writing that the <br />entire Work is substantially complete (except for items <br />specifically listed by CONTRACTOR as incomplete) <br />and request that ENGINEER issue a certificate of <br />Substantial Completion. Promptly thereafter, <br />OWNER, CONTRACTOR, and ENGINEER shall <br />make an inspection of the Work to determine the <br />status of completion. If ENGINEER does not consider <br />the Work substantially complete, ENGINEER will <br />notify CONTRACTOR in writing giving the reasons <br />therefore. if €�'.o;NEER— ansiders the --Work <br />substantiallyy-- GvFicPI�, ENGINEERwill prepare n,crrrr � <br />deliver t9 OWNER �i tentative GerfifiGate of Substanfia4 <br />Completion whiGh shall fix the date of Substantial <br />Completion. There shall be attaGhed to the GertifiGat <br />before final payment. OWNER shall have seven days <br />make 'Ken b'erfien to ENGINEER as +o an <br />rTRncri=iiT,iccn��cvllvl"f—cv—cr ENGINEER � c C, c a.. w ..... � <br />previsiens of the GeFtifirate OF attarhed list. if, after <br />that—the Work isRot substantially GOMpleteT <br />ENGINEER will within 14 days after submissii+n 0+ham <br />tentative GeFtifiGate to OWNER notify CONTRAGTOR <br />ii-wr'+'nn stating the reasons �c�=c—.If <br />Gensiders fihe--Wo substantially plete, <br />€l'1f�€€R uAl Tsaid 14 days enenute–aad <br />deliver tG OWNER and GONTRACT-OR a definitive <br />tentative list of items to be Gempleted OF GOFFeGted) <br />Fefler+'no such nhan s frem the tentative ner+ifirn+e <br />F=h'QlAICCD believe justified after ronsidere+ion of <br />any ebjeGtiens frern OWNER. At the time of delivery <br />of the tentative GeFtifiGate ef Substantial Completion <br />ENGINEER will deliver +o OWNER and GONTDAr <br />TQ- R yfri#eri FeGGIFFIrriendation as to division of <br />respoLsib'1�es_pending final payrnem hefiuven <br />eperatieri, safety, and preteGtien of the Work, <br />mea�ne, heat, 414�i nc�ir�nn��n��i�n�nties <br />�unala�+ I�rOWlERand <br />CONTRACT <br />�Fiting arid so <br />inform ENGINEER irpn prior to ENGINEER'c <br />ins, in the definitive e.f'firate of Substantial Gemple_ <br />fiep ENGINEER's 'foresaid dateen will b <br />�v,T�rcvmcrn v-mvrcvrnvTcvvriTrirc�'n�vaivr� cin, ocbinding on OWNER and CONTRACTOR until firial <br />B. OWNER shall have the right to exclude <br />CONTRACTOR from the Site after the date of <br />Substantial Completion, but OWNER shall allow CON= <br />TRACTOR reasonable access to complete or correct <br />items on the tentative list. <br />14.05 Partial Utilization <br />A. Use by OWNER at OWNER's option of any <br />substantially completed part of the Work which has <br />specifically been identified in the Contract Documents, <br />or which OWNER, ENGINEER, and CONTRACTOR <br />agree constitutes a separately functioning and usable <br />part of the Work that can be used by OWNER for its <br />intended purpose without significant interference with <br />CONTRACTOR's performance of the remainder of <br />the Work, may be accomplished prior to Substantial <br />Completion of all the Work subject to the following <br />conditions. <br />1. OWNER at any time may request <br />CONTRACTOR in writing to permit OWNER to <br />use any such part of the Work which OWNER <br />believes to be ready for its intended use and <br />substantially complete. If CONTRACTOR <br />agrees that such part of the Work is <br />substantially complete, CONTRACTOR will <br />certify to OWNER and ENGINEER that such <br />part of the Work is substantially complete and <br />request ENGINEER to issue a certificate of <br />Substantial Completion for that part of the <br />Work. CONTRACTOR at any time may notify <br />OWNER and ENGINEER in writing that <br />CONTRACTOR considers any such part of the <br />Work ready for its intended use and substan- <br />tially complete and request ENGINEER to issue <br />a certificate of Substantial Completion for that <br />part of the Work. Within a reasonable time <br />after either such request, OWNER, <br />CONTRACTOR, and ENGINEER shall make <br />an inspection of that part of the Work to <br />determine its status of completion. if <br />ENGINEER does not consider that part of the <br />Work to be substantially complete, ENGINEER <br />will notify OWNER and CONTRACTOR in <br />writing giving the reasons therefor. If <br />ENGINEER considers that part of the Work to <br />be substantially complete, the provisions of <br />paragraph 14.04 will apply with respect to <br />certification of Substantial Completion of that <br />part of the Work and the division of <br />responsibility in respect thereof and access <br />thereto. <br />2. No occupancy or separate operation <br />of part of the Work may occur prior to <br />00700 - General Conditions REV 510-13 <br />00700-41 <br />FAPublic Works\ENGINEERING DIVISION PROJECTS\1719 Atlantic Blvd Parkng Area_Project\1-Admin\Bid Documents\Nlaster Contract Documents\00700 General Conditions REV 510- <br />13.doc - <br />