Contract# IRL2018-13 <br />Encumbrance#s GLO1-1701($36,000) & GLOI-1895($25,000) <br />VII. BUDGET <br />The engineer's preliminary construction cost for the project is presented below. <br />JONES' PIER WETLAND RESTORATION <br />ESTIMATE OF CONSTRUCTION COST BASED ON CONCEPTUAL PLAN <br />Description <br />tem <br />uanti <br />Unit <br />Unit Price <br />Total <br />Site Construction <br />$139,455.00 <br />$3,200.00 <br />2 <br />Preparation of Interim & Final Reports <br />Mobilization <br />1 <br />LS <br />$7,500.00 <br />$7,500.00 <br />Clearing (Based on Wetland Restoration area <br />3.8 <br />AC <br />$3,000.00 <br />$11,40-0-00 <br />Haul Clearing Debris off-site and disposal <br />1 <br />LS <br />$3,500.00 <br />$3,500.00 <br />Pond Excavation 3 ponds -based on 6' depth <br />14,500 <br />CY <br />$4.00 <br />$58,000.00 <br />Haul Fill on-site and stockpile and depth of 6' <br />14,500 <br />CY <br />$2.00 <br />$29,000.00 <br />Rough Gradin Site <br />3.8 <br />AC <br />$2,000.00 <br />$7,600.00 <br />Final Gradin Pond contouring - per pond <br />3 <br />EA <br />$7,500.00 <br />$22 500.00 <br />Subtotal <br />$139500.00 <br />Storm Drainage & Erosion Control <br />12" ADS N-12 for pond outfall pipe <br />100 <br />LF <br />$23.00 <br />$2,300.00 <br />18" ADS N-12 pond connector pipes <br />200 <br />LF <br />$34.00 <br />$6,800.00 <br />Stabilized road restoration for pipe install <br />1 <br />LS <br />$6,500.00 <br />$6,500.00 <br />Solar Pump house / system <br />1 <br />EA <br />$4,000.00 <br />$4,000.00 <br />Control Structure <br />1 <br />EA <br />$2,500.00 <br />$2,500.00 <br />Erosion Control <br />1 <br />LS <br />$3,500.00 <br />Planting <br />__L$3,500.00 <br />Subtotal <br />$25,600.00 <br />Procure & Install Plant Materials 1 <br />LS $23,355.00 $23.3550.00 <br />Professional Services <br />__ Subtotal $23,355.00 <br />Survey Stakeout <br />1 <br />LS <br />$6,000.00 <br />$6,000.00 <br />Engineer Coord. and meetings through Phase I <br />Construction <br />1 <br />LS <br />$6,000.00 <br />$6,000.00 <br />Subtotal <br />TOTAL <br />$12,000.00 <br />$200,455.00 <br />An overall summary of the costs included in the grant application request are included below. <br />Task <br />Description <br />IRL NEP <br />Funding <br />IRC Cash <br />Contribution <br />IRC In -Kind <br />Servicesl <br />1 <br />Project Construction <br />$61,000.00 <br />$139,455.00 <br />$3,200.00 <br />2 <br />Preparation of Interim & Final Reports <br />$0.00 <br />$0.00 <br />$3,500.00 <br />3 <br />Baseline Data Collection & Report <br />$0.00 <br />$0.00 <br />$2,500.00 <br />4 <br />Design of Educational Exhibits <br />$0.00 <br />$0.00 <br />$3,000.00 <br />5 <br />Construction of Educational Exhibits <br />$0.00 <br />$3,000.00 <br />$4,500.00 <br />Summary Cost <br />$61,000.00 <br />$142,455.00 <br />$16,700.00 <br />Project Total Cost <br />$220,155.00 <br />1 - The County has funded $37,150.00 towards the completion of the Master Plan & development of the Conceptual <br />Design. Final Design & Permitting is anticipated to include approximately $25,000.00 of contractor fees and in kind <br />services, which is not included in the budget presented above. <br />Page 19 156 <br />