Laserfiche WebLink
EXHIBIT `3' <br />TIME SCHEDULE. <br />WORK ORDER NO.3 <br />Time of Performance <br />The estimated time frame for completion of services from. the. approval of this Work <br />Order is as follows: <br />Task 1— Survey and Base :Plan Preparation: <br />Utility locates, route survey, excavation/"pot holing", 4'/z Months <br />backfill, regrade and grass disturbed areas, survey of <br />utilities, base plan preparation <br />Task 2 — Preliminary Engineering — Re -Use Main Route: <br />Base plan evaluation, soil borings, preliminary 1 %2' Months <br />construction plan, cost estimate, preliminary <br />report of findings <br />Task 3 — Preliminary Engineering — Hydraulic Model / <br />System Recommendation / Final Report: <br />Evaluation of service area, hydraulic analysis/model N2 Months <br />of IRCDUS re=use water system, revise/update preliminary <br />construction plans and cost estimate, prepare .final report, <br />attend BCC and other public meetings (as required) <br />Remainder of Page Intentionally Left Blank <br />P. 1 of 1 <br />122 <br />