Indian River County Solid Waste Disposal District <br />Bid / Pay Items <br />Contract No. 2018025 <br />Change Order No. 2 <br />Lines that have Owner Direct Purchase are in blue. <br />Item <br />Unit <br />Estimated <br />Quantity <br />Unit Price <br />Original Total <br />Change Order <br />No.2 <br />Revised Unit Price <br />New Total after CO <br />No. 2 <br />BID ITEMS: <br />1. SEGMENT 3 CELL 2 EXPANSION <br />1A. Site Work <br />a. Site Preparation, Clearing, Grubbing <br />L.S. <br />1 <br />a.1 Site Preparation <br />$20,000.00 <br />520,000.00 <br />$20,000.00 <br />$20,000.00 <br />a.1 Site Clearing <br />$30,000.00 <br />$30,000.00 <br />530,000.00 <br />$30,000.00 <br />b. Site Grading <br />L.S. <br />1 <br />560,000.00 <br />$60,000.00 <br />. $60,000.00 <br />$60,000.00 <br />c. Imported Common Fill -Subgrade <br />C.Y. <br />44,000 <br />$12.00 <br />$528,000.00 <br />512.00 <br />$528,000.00 <br />d. Interim Cell Stormwater Diversion Berm <br />L.F. <br />335 <br />$125.00 <br />541,875.00 <br />$125.00 <br />541,875.00 <br />e. 24 -inch by 36 -inch Elliptical, RCP Culvert <br />L.F. <br />200 <br />5140.00 <br />528,000.00 <br />-515,059.60 <br />$64.70 <br />512,940.40 <br />f. Fabric Formed Concrete Riprap <br />S.F. <br />150 <br />510.00 <br />51,500.00 <br />510.00 <br />51,500.00 <br />g. Coquina Shell Access Road and Shoulder <br />S.F. <br />4,050 <br />$2.00 <br />58,100.00 <br />$2.00 <br />$8,100.00 <br />1B. Liner System <br />$0.00 <br />a. 6 -inch Processed Sand Layer <br />C.Y. <br />11,500 <br />$26.00 <br />5299,000.00 <br />$26.00 <br />$299,000.00 <br />b. Geosynthetic Clay Liner <br />S.F. <br />494,000 <br />$0.57 <br />5281,580.00 <br />-5193,776.90 <br />50.1777 <br />587,803.10 <br />c. Secondary 60 -mil Textured HDPE Geomembrane <br />S.F. <br />494,000 <br />$0.50 <br />$247,000.00 <br />-5177,271.17 <br />50.1412 <br />$69,728.83 <br />d. LDS Geonet <br />S.F. <br />389,000 <br />50.41 <br />5159,490.00 <br />-5122,121.96 <br />$0.0961 <br />$37,368.04 <br />e. LDS Geocomposite Double Sided <br />S.F. <br />105,000 <br />50.71 <br />$74,550.00 <br />-558,760.13 <br />50.1504 <br />515,789.87 <br />f. Primary 60 -mil Textured H 0 P6, Geomembra ne <br />5.F. <br />494,000 <br />$0.50 <br />5247,000.00 <br />-$177,271.18 <br />50.1412 <br />$69,728.82 <br />g. LCS Geocomposite Double Sided <br />S.F. <br />494,000 <br />50.67 <br />5330,980.00 <br />-5267,215.27 <br />50.1291 <br />$63,764.73 <br />h. 24 -inch Protective Sand Cover <br />C.Y. <br />49,000 <br />$45.00 <br />$2,205,000.00 <br />545.00 <br />$2,205,000.00 <br />i. Tie-in to Existing Cell (inclusive of all layers) <br />L.S. <br />1 <br />$25,000.00 <br />525,000.00 <br />$25,000.00 <br />$25,000.00 <br />j. Metal Information Signs <br />Ea. <br />10 <br />$500.00 <br />55,000.00 <br />$500.00 <br />$5,000.00 <br />k. Electrical Leak Location Survey <br />L.S. <br />1 <br />531,000.00 <br />531,000.00 <br />531,000.00 <br />531,000.00 <br />I. Cleaning and Video Inspection of the Leachate Collection <br />and Leachate Detection Systems <br />L.S. <br />1 <br />$5,100.00 <br />55,100.00 <br />$5,100.00 <br />$5,100.00 <br />m. Site Restoration Including Sod <br />L.S. <br />1 <br />$45,000.00 <br />$45,000.00 <br />$45,000.00 <br />$45,000.00 <br />n. Miscellaneous <br />LS. <br />1 <br />$0.00 <br />$0.00 <br />$0.00 <br />1C, Leachate Detection System (LDS) Pump Station <br />50.00 <br />a. LDS Pump Station Pump Package Including all <br />components for a complete system (wetwell, hatch and <br />safety grate, turbine meter with totalizer, 1.5 -Inch <br />Schedule 80 PVC pipe and fittings, and control panel) <br />Ea. <br />1 <br />$150,000.00 <br />5150,000.00 <br />-57,081.64 <br />5142,918.36 <br />5142,918.36 <br />b. 18 -Feet x 13 -Feet x 10 -Inch Thick Concrete Slab <br />S.F. <br />234 <br />$25.00 <br />55,850.00 <br />$25.00 <br />$5,850.00 <br />c. Miscellaneous <br />L.S. <br />1 <br />$7,000.00 <br />$7,000.00 <br />57,000.00 <br />$7,000.00 <br />1D. Leachate Piping System <br />' <br />$0.00 <br />a. Leak Detection System including 50915.5 HDPE Pipe, <br />Fittings, Geotextile wrap, River Rock, Bootless Pipe <br />Penetration, Cleanouts <br />L.S. <br />1 <br />$150,000.00 <br />$150,000.00 <br />-553,738.08 <br />596,261.92 <br />596,261.92 <br />b. Leachate Collection System including SDR 15.5 HDPE <br />' Pipe and Fittings, Geotextile wrap, River Rock, Bootless <br />Pipe Penetration, Cleanout, Plug Valves <br />L.S. <br />1 <br />520,000.00 <br />520,000.00 <br />-$1,436.81 <br />$18,563.19 <br />518,563.19 <br />c. 5 -Foot Diameter LCS Manhole <br />Ea. <br />2 <br />520,000.00 <br />540,000.00 <br />-514,317.73 <br />$12,841.14 <br />525,682.27 <br />d. Horizontal Directional Drill 10 -Inch Solid SDR 15.5 HDPE <br />Gravity Pipe <br />L.F. <br />100 <br />5100.00 <br />510,000.00 <br />5100.00 <br />$10,000.00 <br />e. Miscellaneous <br />L.S. <br />1 <br />50.00 <br />50.00 <br />$0.00 <br />1E. Electrical and Instrumentation and Control <br />_ <br />$0.00 <br />a. Measurement and Control Instrumentation <br />-." <br />._ <br />_-, _ <br />- - ....50.00 <br />- <br />a.1. Programming Points <br />Ea. <br />. 29 <br />51,500.00 <br />$43,500.00 <br />51,500.00 <br />$43,500.00 <br />a.2. lnstruments <br />Ea. <br />16 <br />515,000.00 <br />$240,000.00 <br />515,000.00 <br />$240,000.00 <br />a.3. Tower and Antenna <br />Ea. <br />1 <br />$25,000.00 <br />$25,000.00 <br />525,000.00 <br />$25,000.00 <br />b. Electrical Demolition Including Removal and Disposal <br />L.S. <br />1 <br />$600.00 <br />$600.00 <br />$600.00 <br />$600.00 <br />c. Grounding <br />L.F. <br />520 <br />511.00 <br />$5,720.00 <br />511.00 <br />$5,720.00 <br />d. Service & Distribution <br />50.00 <br />d.1.Panelboard PP -1 <br />Ea. <br />1 <br />515,000.00 <br />.$15,000.00 <br />-$14,310.00 <br />$690.00 <br />$690.00 <br />d.2. Main Circuit Breaker <br />Ea. <br />1 <br />52,000.00 <br />$2,000.00 <br />-51,272.00 <br />$728.00 <br />$728.00 <br />d.3. ATS <br />Ea. <br />1 <br />$11,000.00 <br />511,000.00 <br />-58,945.34 <br />$2,054.66 <br />52,054.66 <br />d.4.TPA-COMP-A <br />Ea. <br />1 <br />58,000.00 <br />$8,000.00 <br />-56,360.00 <br />51,640.00 <br />51,640.00 <br />d.5.TPA-LCS-A <br />Ea. <br />1 <br />$10,000.00 <br />510,000.00 <br />-59,407.83 <br />5592.17 <br />5592.17 <br />d.6. Panelboard LP -LDS <br />Ea. <br />1 <br />$4,000.00 <br />$4,000.00 <br />-$4,000.00 <br />$0.00 <br />50.00 <br />d.7. Mounting Racks <br />Ea. <br />3 <br />510,000.00 <br />$30,000.00 <br />-520,101.60 <br />$3,299.47 <br />$9,898.40 <br />d.8. 20KW Diesel Genset <br />Ea. <br />1 <br />550,000.00 <br />550,000.00 <br />-550,000.00 <br />$0.00 <br />- $0.00 <br />e. Site Power <br />- _ , <br />$0.00 <br />Smith <br />12193_01t 1.slse <br />®21118 CDM Smith Inc. <br />All Rights Reserved <br />lof 3 <br />