Laserfiche WebLink
BOOK W PAa 896 <br />DESCRIPTION AND CONDITIONS <br />As the Board of Commissioners will recall there was difficulty in <br />determining the correct earth work quantities during contract <br />bidding. The figures were revised based on survey work done by the <br />county to check the ditch relocation. These figures were not <br />adjusted in order to provide a safety factor, other than for the <br />expected shrinkage factor, so that imbalanced bids could not be <br />submitted. All possible sources of fill from the job have been used <br />except from the ditch construction on the south side of CR 512, and <br />it is clear more earth will be needed to complete the job <br />especially the berm construction. <br />The current contract amount including Change Order 1 is <br />$2,752,616.24. This Change Order for up to 12500 CY of Borrow and <br />$31,750.00 makes the new contract amount $2,784,366.24. This Change <br />Order includes the full cost of maintenance dredging of the Collier <br />Creek area in the County Right of Way which was requested as <br />additional work by the county, and amounted to $3,300 which was all <br />included in the Borrow item 120-2-3 as that item was used to build <br />an access ramp to the area of work. <br />ALTERNATIVES AND ANALYSIS <br />The following alternatives are presented: <br />Alternative 1: Approve Change Order 2 to the contract and authorize <br />the Chairman to execute Change Order 2 on behalf of the Board. <br />Alternative 2: Do not approve the change order. <br />RECOMMENDATION AND FUNDING <br />Staff recommends Alternative 1, funding to be from account number <br />101-153-541-067.38. <br />ON MOTION by Commissioner Adams, SECONDED by <br />Commissioner Macht, the Board by a 4-0 vote <br />(Commissioner Eggert being absent), approved Change <br />Order No. 2 with Martin Paving Company in the amount <br />of $31,750, as recommended by staff. <br />CHANGE ORDER NO. 2 IS ON FILE <br />IN THE OFFICE OF THE CLERK TO THE BOARD <br />INDIAN RIVER BOULEVARD PHASE IV CONSTRUCTION <br />MATERIALS TESTING <br />The Board reviewed a Memorandum of November 28, 1994: <br />40 <br />DECEMBER 6, 1994 <br />