ANALYSIS: <br />Most, but not all, of the required project improvements have been completed. As provided for under <br />the LDRs applicable to this final plat application, the applicant will be "bonding -out" the remaining <br />18.77% of required project improvements (drainage, landscaping, roadways, utilities). Public Works, <br />Utility Services, and Planning have reviewed and approved the submitted Engineer's Certified Cost <br />Estimate for the remaining project improvements. Staff anticipates receipt of the Contract for <br />Construction of Required Improvements and an acceptable letter of credit in the amount of 125% of <br />the cost of construction for the remaining required improvements prior to the December 181h Board <br />meeting. However, because the December 18th meeting is the last meeting of the calendar year, those <br />items may be provided after the December 181h meeting. The contract for construction will be executed <br />by the County Administrator once the acceptable security has been received and approved by the <br />County Attorney's Office. The final plat will not be executed by the Chairman of the Board until these <br />items have been addressed. <br />All improvements within The Willows Phase 2 will be private, with the exception of certain utility <br />facilities. Those utility facilities will be dedicated to and guaranteed to Indian River County as required <br />by the Utility Services Department. <br />RECOMMENDATION: <br />Staff recommends that the Board grant final plat approval for The Willows Phase 2, subject to final <br />review, approval, and signoff of a Contract for Construction of Required Improvements and acceptable <br />letter of credit by the County Attorney's Office. <br />ATTACHMENTS: <br />1. Application <br />2. Location Map <br />3. Final Plat Layout <br />C:\Users\legistar\AppData\L4ocal\Temp\BCL Technologies\easyPDF 8\@BCL@440E6294\@BCL@440E6294.docx 85 2 <br />