Timeline/ Summary <br />im Determination of ROW <br />• Issuance of Temporary Construction Easement <br />11. Submittal to FDEP for review <br />FDEP issuance of ERP <br />• Note: Stakeholders have verbally stated the ERP will be challenged <br />through the DOAH process: 11-12 months per FDEP <br />N. Mosquito District/BCC agreement: F.S. 164 Process? <br />UCP issues need to be settled <br />IRC ROW permit still required <br />