Boa 94 PAul 324 <br />ON MOTION by Commissioner Eggert, SECONDED by <br />Commissioner Bird, the Board unanimously (4-0, <br />Chairman Macht being absent) approved Change Order <br />No. 1 and Final Payment to Driveways, Inc. in the <br />amount of $22,769.62, as recommended by staff. <br />CHANGE ORDER #1 IS ON FILE IN THE OFFICE OF THE CLERK TO THE BOARD <br />NORTH COUNTY R.O. - PHASE H - WELL FIELD MASTER PLAN <br />AND WELL CONSTRUCTION - MISSEWER INTERNATIONAL INC. <br />The Board reviewed the following memo dated 1/16/95: <br />DATE: JANUARY 16, 1995 <br />TO: JAMES E. CHANDLER <br />COUNTY ADMINISTRATOR <br />FROM: TERRANCE G. ZL <br />DIRECTOR OF I ' SERVICES <br />PREPARED WILLIAM F. MZfi IN <br />AND STAFFED CAPITAL PROJEC E EER <br />BY: DEPARTMENT ITY SERVICES <br />SUBJECT: NORTH COUNTY R.O. PHASE II - NORTH COUNTY WELL FIELD <br />MASTER PLAN AND WELL CONSTRUCTION <br />INDIAN RIVER COUNTY PROJECT NO. UW -94 -03 -WC <br />In May of 1994 the Indian River County Board of County Commissioners <br />approved the design of Phase II of the North County R.O. Plant <br />(i.e., the actual water processing facility). At that same time <br />(see attached agenda item and minutes), we stated what additional <br />design would be needed and were approved for these additional work <br />items, one of which was for the plant well field. We have completed <br />the RFP consultant selection process for this work and would like to <br />proceed. The No. 1 ranked firm for this project was Missimer <br />International, Inc., and we have completed negotiations on a <br />proposed contract with them. <br />ANALYSIS <br />The requested scope of services is outlined on the attached RFP and <br />in the proposed contract. Our water plant consultant was charged <br />with the initial consumptive use permit application to St. Johns <br />River Water Management District. The District has responded to this <br />application, and our contract with Missimer directly reflects this <br />response. The work over and above this response and that associated <br />wells design/construction is for the well field Master plan layout. <br />Please see the attached work authorization with Missimer <br />International, Inc. Total project cost breakdown can be found in <br />the budget section of the work authorization in -detail. The general <br />costs are as follows: <br />FEBRUARY 7, 1995 105 <br />