EXHIBIT C — TIME SCHEDULE <br />In general, the following schedule is anticipated and consultant will work as expeditiously as <br />possible to meet a mutually agreed upon schedule: <br />Task 1 — <br />Update the Water System Hydraulic Model <br />12 weeks from NTP <br />Task 2 — <br />Calibrate the Water System Hydraulic Model <br />16 weeks from NTP <br />Task 3 — <br />Additional Existing System Model Development <br />22 weeks from NTP <br />Task 4 — <br />Model Evaluation/Report Preparation <br />32 weeks from NTP <br />Task 5 — <br />Limited Unidirectional Flushing Maps <br />32 weeks from NTP <br />54 <br />