Laserfiche WebLink
Work Order No. 32 <br />HHW/Recycling Concept <br />EXHIBIT C - TIME SCHEDULE <br />Upon authorization to proceed by the COUNTY, final documents are anticipated to take <br />approximately two (2) months from the Notice to Proceed (NTP). <br />NTP contingent upon approval <br />Existing Conditions Assessment 30 days from NTP <br />Site Plan Alternatives/Order-of-Magnitude Costs 45 days from NTP <br />Conceptual Plans and Planning OPC 60 days from NTP <br />This Agreement is made in anticipation of conditions permitting continuous and orderly <br />progress through completion of the services. Times for performance shall be extended as <br />necessary for delays or suspensions. Notwithstanding any other provision of this Agreement, <br />the Consultant shall not have liability for or be deemed in breach because of delays caused by <br />any factor outside of its reasonable control. <br />(THE REMAINDER OF THIS PAGE IS INTENTIONALLY BLANK) <br />Page 6 of 6 <br />