ARTICLE 9 - CONTRACT TIMES <br />9.01 The number of calendar days within which, or the dates by which, the Work is to be (a) <br />Substantially Completed and (b) also completed and ready for final payment are set forth in the <br />Agreement. <br />ARTICLE 10 - LIQUIDATED DAMAGES <br />10.01 Provisions for liquidated damages, if any, are set forth in the Agreement. <br />ARTICLE 11 - SUBSTITUTE AND "OR -EQUAL" ITEMS <br />11.01 The Contract, if awarded, will be on the basis of materials and equipment specified or <br />described in the Bidding Documents without consideration of possible substitute or "or -equal" <br />items. Whenever it is specified or described in the Bidding Documents that a substitute or "or - <br />equal" item of material or equipment may be furnished or used by CONTRACTOR if acceptable to <br />ENGINEER, application for such acceptance will not be considered by ENGINEER until after the <br />Effective Date of the Agreement. The procedure for submission of any such application by <br />CONTRACTOR and consideration by ENGINEER is set forth in the General Conditions and may <br />be supplemented in the General Requirements. <br />ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS <br />12.01 If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, <br />individuals, or entities to be submitted to OWNER in advance of a specified date prior to the <br />Effective Date of the Agreement, the apparent Successful Bidder, and any other Bidder so <br />requested, shall within five days after Bid opening, submit to OWNER a list of all such <br />Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work for <br />which such identification is required. Such list shall be accompanied by an experience statement <br />with pertinent information regarding similar projects and other evidence of qualification for each <br />such Subcontractor, Supplier, individual, or entity if requested by OWNER. If OWNER or <br />ENGINEER, after due investigation, has reasonable objection to any proposed Subcontractor, <br />Supplier, individual, or entity, OWNER may, before the Notice of Award is given, request apparent <br />Successful Bidder to submit a substitute, without an increase in the Bid. <br />12.02 If apparent Successful Bidder declines to make any such substitution, OWNER may award <br />the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, <br />individuals, or entities. Declining to make requested substitutions will not constitute grounds for <br />forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so <br />listed and against which OWNER or ENGINEER makes no written objection prior to the giving of <br />the Notice of Award will be deemed acceptable to OWNER and ENGINEER subject to revocation <br />of such acceptance after the Effective Date of the Agreement as provided in paragraph 6.06 of the <br />General Conditions. <br />00200 - Instructions to Bidders REV 04-07 <br />00200-6 <br />F:\Public Works\ENGINEERING DIVISION PROJECTS\1325 58th Avenue (57th St to CR 510) Roadway Inventory\1- <br />Admin\Bids\Bid Documents\00200 - Instructions to Bidders REV 04-07.doc <br />