Page 1 of 2 <br />SECTION 00942 — Change Order Form <br />No. 1 <br />DATE OF ISSUANCE: 7/02/2019 EFFECTIVE DATE: 7/02/2019 <br />OWNER: Indian River County <br />CONTRACTOR COMMUNITY ASPHALT. CORP. <br />Project: CR 612 RESURFACING & SHOULDER WIDENING FROM MYRTLE <br />STREET TO 126, AVENUE <br />OWNER's Project No. IRC -1305 <br />OWNER'S Bid No. 2018009 <br />FM No: 433068-1-64-01 <br />You are directed to make the following changes in the Contract Documents: <br />Description: <br />1. Relocate Storm Drain at CR -512 and Willow Street intersection as detailed in plan sheet <br />1 of "CR -512 Resurfacing & Shoulder Widening from Myrtle Street to 125th Avenue — <br />Drainage Fix, Sheet 1. <br />Item: Pipe Relocation — Lump Sum - $135,987.39 <br />2. Revise Strain Pole heights to ensure minimum roadway clearance and increase in plan <br />quantity. <br />Item: Concrete Strain Pole Change — Lump Sum - $43,065.00 <br />3. Provide Maintenance of Traffic for additional contract time of 242 days. <br />Item: MOT — Lump Sum - $24,354.28 <br />4. Extend Contract time for 242 days <br />a. Weather related delay days and Holidays — 46 Days <br />b. Extension for utility delays from AT&T/Comcast relocation — 57 Days <br />c. Extension for redesign and contract change order - 22 Days <br />d. Temporary contract holding time — 42 Days <br />e. Extension for relocation of drainage and associated mast arm schedule impacts, <br />including manufacture and delivery of drainage structures — 53 Days <br />f. Extension for mast arm installation and additional restoration work — 22 Days <br />Reason for Change Order: <br />1. Addressing the relocation of the storm drain to make room for the mast arm foundation <br />in the north west comer of CR 512 and Willow Street intersection. <br />2. Change of Strain Pole Height to have adequate clearance for trucks. <br />3. Contract time is being extended 242 days. This covers project -wide general <br />maintenance of traffic required in order to ensure a safe work zone. <br />4. Extension of Contract Time to accommodate all utility conflict, design change, material <br />manufacturing delays associated with the work detailed in this work order. <br />Items shall include all associated costs with completing the work listed and shown on drawings <br />and related time extensions as detailed within this change order such as installation, all labor, <br />construction equipment and materials, and incidentals necessary to perform the work. <br />IRC -1305 Col 20190702 <br />00942-1 <br />F:V%U1G V Vork9AMINEERINO DIVISION PROJECTS11366•CR 612 R9%d (SCOPLMyrUe St b 126th SM44*01\yenda IIw*riwpe Ord9mUwge Order No. 1VRC- <br />1306 CO1 2019070Zdoo Rev. 03M <br />