thereof) to be constructed in accordance with the
<br />Contract Documents. Any labor, documentation,
<br />services, materials, or equipment that may
<br />reasonably be inferred from the Contract Documents
<br />or from prevailing custom or trade usage as being
<br />required to produce the intended result will be
<br />provided whether or not specifically called for at no
<br />additional cost to OWNER.
<br />C. Clarifications and � interpretations of the
<br />Contract Documents shall be issued by ENGINEER
<br />as provided in Article 9.
<br />3.02 Reference Standards
<br />A. Standards, Specifications, Codes, Laws, and
<br />Regulations
<br />1. Reference to standards, specifica-
<br />tions, manuals, or codes of any technical
<br />society, organization, or association, or to
<br />Laws or Regulations, whether such reference
<br />be specific or by implication, shall mean the
<br />standard, specification, manual, code, or Laws
<br />or Regulations in effect at the time of opening
<br />of Bids (or on the Effective Date of the
<br />Agreement if there were no Bids), except as
<br />may be otherwise specifically stated in the
<br />Contract Documents.
<br />2. No provision of any such standard,
<br />specification, manual or code, or any
<br />instruction of a Supplier shall be effective to
<br />change the duties or responsibilities of
<br />OWNER, CONTRACTOR, or ENGINEER, or
<br />any of their subcontractors, consultants,
<br />agents, or employees from those set forth in
<br />the Contract Documents, nor shall any such
<br />provision or instruction be effective to assign to
<br />OWNER, ENGINEER, or any of ENGINEER's
<br />Consultants, agents, or employees any duty or
<br />authority to supervise or direct the performance
<br />of the Work or any duty or authority to
<br />undertake responsibility inconsistent with the
<br />provisions of the Contract Documents.
<br />3.03 Reporting and Resolving Discrepancies
<br />A. Reporting Discrepancies
<br />1. If, during the performance of the
<br />Work, CONTRACTOR discovers any conflict,
<br />error, ambiguity, or discrepancy within the Con-
<br />tract Documents or between the Contract
<br />Documents and any provision of any Law or
<br />Regulation applicable to the performance of
<br />the Work or of any standard, specification,
<br />manual or code, or of any instruction of any
<br />Supplier, CONTRACTOR shall report it to
<br />ENGINEER in writing at once. CONTRACTOR
<br />shall not proceed with the Work affected
<br />thereby (except in an emergency as required
<br />by paragraph 6.16.A) until an amendment or
<br />supplement to the Contract Documents has
<br />been issued by one of the methods indicated in
<br />paragraph 3.04; provided, however, that
<br />CONTRACTOR shall not be liable to OWNER
<br />or ENGINEER for failure to report any such
<br />conflict, error, ambiguity, or discrepancy unless
<br />CONTRACTOR knew or reasonably should
<br />have known thereof.
<br />B. Resolving Discrepancies
<br />1. Except as may be otherwise
<br />specifically stated in the Contract Documents,
<br />the provisions of the Contract Documents shall
<br />take precedence in resolving any conflict, error,
<br />ambiguity, or discrepancy between the
<br />provisions of the Contract Documents and:
<br />a. the provisions of any standard,
<br />specification, manual, code, or instruction
<br />(whether or not specifically incorporated by
<br />reference in the Contract Documents); or
<br />b. the provisions of any Laws or
<br />Regulations applicable to the performance
<br />of the Work (unless such an interpretation
<br />of the provisions of the Contract Documents
<br />would result in violation of such Law or
<br />Regulation).
<br />3.04 Amending and Supplementing Contract
<br />Documents
<br />A. The Contract Documents may be amended
<br />to provide for additions, deletions, and revisions in the
<br />Work or to modify the terms and conditions thereof in
<br />one or more of the following ways: (i) a Written
<br />Amendment; (ii) a Change Order; or (iii) a Work
<br />Change Directive.
<br />B. The requirements of the Contract Documents
<br />may be supplemented, and minor variations and
<br />deviations in the Work may be authorized, by one or
<br />more of the following ways: (0) a Gold ^ ; (ii)
<br />ENGINEER's approval of a Shop Drawing or Sample;
<br />or (iii) ENGINEER's written interpretation or clarifi-
<br />cation.
<br />3.05 Reuse of Documents
<br />A. CONTRACTOR and any Subcontractor or
<br />Supplier or other individual or entity performing or