Project, shall include only the following items, and
<br />shall not include any of the costs itemized in para-
<br />graph 11.01.13.
<br />2. Cost of all materials and equipment
<br />furnished and incorporated in the Work, includ-
<br />ing costs of transportation and storage thereof,
<br />and Suppliers' field services required in
<br />connection therewith. All cash discounts shall
<br />accrue to CONTRACTOR unless OWNER
<br />deposits funds with CONTRACTOR with which
<br />to make payments, in which case the cash
<br />discounts shall accrue to OWNER. All trade
<br />discounts, rebates and refunds and returns
<br />from sale of surplus materials and equipment
<br />shall accrue to OWNER, and CONTRACTOR
<br />shall make provisions so that they may be
<br />obtained.
<br />3. Payments made by CONTRACTOR
<br />to Subcontractors for Work performed by
<br />Subcontractors. If required by OWNER, CON-
<br />TRACTOR shall obtain competitive bids from
<br />subcontractors acceptable to OWNER and
<br />CONTRACTOR and shall deliver such bids to
<br />OWNER, who will then determine, with the
<br />advice of ENGINEER, which bids, if any, will
<br />be acceptable. If any subcontract provides that
<br />the Subcontractor is to be paid on the basis of
<br />Cost of \the Work plus a fee, the
<br />Subcontractor's Cost of the Work and fee shall
<br />be determined in the same manner as
<br />CONTRACTOR's Cost of the Work and fee as
<br />provided in this paragraph 11.01.
<br />4. Costs of special consultants
<br />(including but not limited to engineers,
<br />architects, testing laboratories, surveyors,
<br />attorneys, and accountants) employed for
<br />services specifically related to the Work.
<br />5. Supplemental costs including the
<br />following:
<br />a. The proportion of necessary trans-
<br />portation, travel, and subsistence expenses of
<br />CONTRACTOR's employees incurred in dis-
<br />charge of duties connected with the Work.
<br />b. Cost, including transportation and
<br />maintenance, of all materials, supplies, equip-
<br />ment, machinery, appliances, office, and
<br />temporary facilities at the Site, and hand tools
<br />not owned by the workers, which are
<br />consumed in the performance of the Work, and
<br />cost, less market value, of such items used but
<br />not consumed which remain the property of
<br />CONTRACTOR.
<br />C. Rentals of all construction equip-
<br />ment and machinery, and the parts thereof
<br />whether rented from CONTRACTOR or others
<br />in accordance with rental agreements
<br />approved by OWNER with the advice of
<br />ENGINEER, and the costs of transportation,
<br />loading, unloading, assembly, dismantling, and
<br />removal thereof. All such costs shall be in
<br />accordance with the terms of said rental agree-
<br />ments. The rental of any such equipment, ma-
<br />chinery, or parts shall cease when the use
<br />thereof is no longer necessary for the Work.
<br />d. Sales, consumer, use, and other
<br />similar taxes related to the Work, and for which
<br />CONTRACTOR is liable, imposed by Laws and
<br />Regulations.
<br />e . Deposits lost for causes other than
<br />negligence of CONTRACTOR, any Sub-
<br />contractor, or anyone directly or indirectly
<br />employed by any of them or for whose acts any
<br />of them may be liable, and royalty payments
<br />and fees for permits and licenses.
<br />f. Losses and damages (and related
<br />expenses) caused by damage to the Work, not
<br />compensated by insurance or otherwise, sus-
<br />tained by CONTRACTOR in connection with
<br />the performance of the Work (except losses
<br />and damages within the deductible amounts of
<br />property insurance established in accordance
<br />with paragraph 5.06.D), provided such losses
<br />00700 - General Conditions REV 5-10-13
<br />00700-32
<br />FAPublic Works%ENGINEERING DIVISION PROJECTS\1727 CR -512 EB & WB Bridge (88407879) Repairs\1-Admin\Bid Documents\Master Contract Documents\00700 - General Conditions
<br />REV 5-10-13.doc
<br />
|