Division 1—General Requirements, IRC -1801A <br />1.4 DISTRIBUTION OF THE CONSTRUCTION SCHEDULES <br />A. After receiving approval bythe ENGINEER, distribute copies of the approved initial <br />schedule and all reviewed revisions (updated) to: <br />1. Job site file. <br />2. Subcontractors. <br />3. Other concerned parties. <br />4. OWNER (two copies). <br />5. ENGINEER <br />B. In the cover letter, instruct recipients to report promptly to the CONTRACTOR, in <br />writing, any problems anticipated by the projections shown in the schedules. <br />+ + END OF SECTION + + <br />Construction Schedules - 01310-2 <br />F:\PublicWorkskENGINEERING DIVISION PROJECTS\1801A IRC Courthouse Parking Garage Rehabilitation\1-Admin\Bids0d Documents\Bid Dcuments\DIV 1 GENERAL <br />REQUIREMENTS.docx — <br />