Laserfiche WebLink
Board of County Commissioners <br />Meeting Minutes - Final September 22, 2020 <br />Attachments: Staff Report <br />APTIM Bid Recommendation Letter 9-15-20 <br />Coastal Tech Recommendation Letter 9-15-20 <br />Public Works Director Richard Szpyrka referred to staffs memorandum dated <br />September 16, 2020, and a PowerPoint presentation to provide an overview of <br />the Sector 3 and Sector 7 Beach and Dune Restoration Projects. He noted that <br />both projects faced challenges obtaining the number of approved easements <br />needed to ensure an effective result. <br />Director Szpyrka then went on to discuss each project in depth, beginning with <br />the bid disparity in the Sector 3 Project. He recounted that the lowest bidder, <br />Ahtna Marine & Construction Company, LLC (Ahtna), had withdrawn their bid <br />after the applicable deadline due to computational errors. The next lowest, <br />qualified bid exceeded the budgeted local contribution and therefore could not <br />be considered. Director Szpyrka reviewed staffs recommendations, and <br />sought the Board's direction. <br />Discussion ensued as the Commissioners received clarification from Director <br />Szpyrka regarding easements, funding and staffs recommendations. Under <br />discussion, Commissioner O'Bryan made a motion to proceed with Sector 3 and <br />award the project to Ahtna; if Ahtna did not honor their bid, staff was <br />authorized to pull the bid bond and proceed with Option 3.B. as detailed in <br />staffs memo. <br />The following people addressed the Board: <br />Tuck Ferrell, Vice Chairman, Indian River County Beach & Shore Preservation <br />Advisory Committee <br />Mark Tripson, 5020 12th Street <br />Tommy King, Rio -Bak Corporation <br />A motion was made by Commissioner O'Bryan, seconded by Vice Chairman <br />Flescher, to approve staffs recommendation to: 1) Award the contract to Ahtna <br />Marine and Construction, LLC (Ahtna) for the Sector 3 Beach and Dune Project; <br />2) If Ahtna refused to honor the bid, staff was authorized to pull the bid bond and <br />proceed with Recommendation 3.B.--re-bid a smaller portion of Sector 3 for <br />completion in 2020/2021, and postpone a re -bid of the remaining portion of <br />Sector 3 until 2021/2022. The motion carried by the following vote: <br />Aye: 5 - Chairman Adams, Vice Chairman Flescher, Commissioner Zorc, Commissioner <br />O'Bryan, and Commissioner Solari <br />Discussion returned to the Sector 7 project with Commissioner O'Bryan's <br />suggestion to delay the project for one year while staff obtained more easements <br />and worked to get extensions on the grant funds; all existing bids would be rejected. <br />Indian River County Florida Page 13 <br />