A. In emergencies affecting the safety or protec-
<br />tion of persons or the Work or property at the Site or
<br />adjacent thereto, CONTRACTOR is obligated to act to
<br />prevent threatened damage, injury, or loss.
<br />CONTRACTOR shall give ENGINEER prompt written
<br />notice if CONTRACTOR believes that any significant
<br />changes in the Work or variations from the Contract
<br />Documents have been caused thereby or are required
<br />as a result thereof. If ENGINEER determines that a
<br />change in the Contract Documents is required be-
<br />cause of the action taken by CONTRACTOR in
<br />response to such an emergency, a Work Change
<br />Directive or Change Order will be issued.
<br />6.17 Shop Drawings and Samples
<br />A. CONTRACTOR shall submit Shop Drawings
<br />to ENGINEER for review and approval in accordance
<br />with the acceptable schedule of Shop Drawings and
<br />Sample submittals. All submittals will be identified as
<br />ENGINEER may require and in the number of copies
<br />specified in the General Requirements. The data
<br />shown on the Shop Drawings will be complete with
<br />respect to quantities, dimensions, specified perfor-
<br />mance and design criteria, materials, and similar data
<br />to show ENGINEER the services, materials, and
<br />equipment CONTRACTOR proposes to provide and to
<br />enable ENGINEER to review the information for the
<br />limited purposes required by paragraph 6.17.E.
<br />B. CONTRACTOR shall also submit Samples to
<br />ENGINEER for review and approval in accordance
<br />with the acceptable schedule of Shop Drawings and
<br />Sample submittals. Each Sample will be identified
<br />clearly as to material, Supplier, pertinent data such as
<br />catalog numbers, and the use for which intended and
<br />otherwise as ENGINEER may require to enable ENGI-
<br />NEER to review the submittal for the limited purposes
<br />required by paragraph 6.17.E. The numbers of each
<br />Sample to be submitted will be as specified in the
<br />Specifications.
<br />C. Where a Shop Drawing or Sample is required
<br />by the Contract Documents or the schedule of Shop
<br />Drawings and Sample submittals acceptable to ENGI-
<br />NEER as required by paragraph 2.07, any related
<br />Work performed prior to ENGINEER's review and
<br />approval of the pertinent submittal will be at the sole
<br />expense and responsibility of CONTRACTOR.
<br />D. Submittal Procedures
<br />1. Before submitting each Shop Drawing
<br />or Sample, CONTRACTOR shall have
<br />determined and verified:
<br />a. all field measurements, quantities,
<br />dimensions, specified performance criteria,
<br />installation requirements, materials, catalog
<br />numbers, and similar information with
<br />respect thereto;
<br />b. all materials with respect to intended
<br />use, fabrication, shipping, handling, storage,
<br />assembly, and installation pertaining to the
<br />performance of the Work;
<br />c. all information relative to means,
<br />methods, techniques, sequences, and
<br />procedures of construction and safety
<br />precautions and programs incident thereto;
<br />and
<br />d. CONTRACTOR shall also have
<br />reviewed and coordinated each Shop
<br />Drawing or Sample with other Shop
<br />Drawings and Samples and with the
<br />requirements of the Work and the Contract
<br />Documents.
<br />2. Each submittal shall bear a stamp or
<br />specific written indication that CONTRACTOR
<br />has satisfied CONTRACTOR's obligations
<br />under the Contract Documents with respect to
<br />CONTRACTOR's review and approval of that
<br />submittal.
<br />3. At the time of each submittal, COW
<br />TRACTOR shall give ENGINEER specific
<br />written notice of such variations, if any, that the
<br />Shop Drawing or Sample submitted may have
<br />from the requirements of the Contract
<br />Documents, such notice to be in a written com-
<br />munication separate from the submittal; and, in
<br />addition, shall cause a specific notation to be
<br />made on each Shop Drawing and Sample sub-
<br />mitted to ENGINEER for review and approval of
<br />each such variation.
<br />E. ENGINEER's Review
<br />1. ENGINEER will timely review and
<br />approve Shop Drawings and Samples in
<br />accordance with the schedule of Shop Drawings
<br />and Sample submittals acceptable to ENGI-
<br />NEER. ENGINEER's review and approval will
<br />be only to determine if the items covered by the
<br />submittals will, after installation or incorporation
<br />in the Work, conform to the information given in
<br />the Contract Documents and be compatible with
<br />the design concept of the completed Project as
<br />a functioning whole as indicated by the Contract
<br />Documents.
<br />2. ENGINEER's review and approval
<br />will not extend to means, methods, techniques,
<br />sequences, or procedures of construction
<br />(except where a particular means, method,
<br />technique, sequence, or procedure of con-
<br />struction is specifically and expressly called for
<br />by the Contract Documents) or to safety
<br />precautions or programs incident thereto. The
<br />General Conditions - 00700 - 19