2. for expenses sustained prior to the
<br />effective date of termination in performing
<br />services and furnishing labor, materials, or
<br />equipment as required by the Contract
<br />Documents in connection with uncompleted
<br />Work, plus fair and reasonable sums for
<br />overhead and profit on such expenses;
<br />3. for all claims, costs, losses, and
<br />damages (including but not limited to all fees
<br />and charges of engineers, architects, attorneys,
<br />and other professionals and all court or
<br />arbitration or other dispute resolution costs) in-
<br />curred in settlement of terminated contracts with
<br />Subcontractors, Suppliers, and others; and
<br />4. for reasonable expenses directly
<br />attributable to termination.
<br />B. CONTRACTOR shall not be paid on account
<br />of loss of anticipated profits or revenue or other eco-
<br />nomic loss arising out of or resulting from such termina-
<br />tion.
<br />15.04 CONTRACTOR May Stop Work or
<br />Terminate
<br />A. If, through no act or fault of CONTRACTOR,
<br />the Work is suspended for more than 90 consecutive
<br />days by OWNER or under an order of court or other
<br />public authority, or ENGINEER fails to act on any
<br />Application for Payment within 30 days after it is
<br />submitted,
<br />then
<br />CONTRACTOR may, upon seven days written notice
<br />to OWNER and ENGINEER, and provided OWNER or
<br />ENGINEER do not remedy such suspension or failure
<br />within that time, terminate the Contract and recover
<br />from OWNER payment on the same terms as provided
<br />in paragraph 15.03. In lieu of terminating the Contract
<br />and without prejudice to any other right or remedy, if
<br />ENGINEER has failed to act on an Application for
<br />Payment within 30 days after it is submitted, er
<br />any Gum fiRally d8t8FMiR8d tQ 138 Gil '44, CONTRACTOR
<br />may, seven days after written notice to OWNER and
<br />ENGINEER, stop the Work until payment is made of all
<br />such amounts due CONTRACTOR, including interest
<br />thereon. The provisions of this paragraph 15.04. are
<br />not intended to preclude CONTRACTOR from making
<br />a Claim under paragraph 10.05 for an adjustment in
<br />Contract Price or Contract Times or otherwise for
<br />expenses or damage directly attributable to
<br />CONTRACTOR's stopping the Work as permitted by
<br />this paragraph.
<br />ARTICLE 16 - DISPUTE RESOLUTION
<br />16.01 Methods and Procedures
<br />A. Dispute resolution methods and procedures, if
<br />any, shall be as set forth in the Supplementary
<br />Conditions. If no method and procedure has been set
<br />forth, and subject to the provisions of paragraphs 9.09
<br />and 10.05, OWNER and CONTRACTOR may
<br />exercise such rights or remedies as either may
<br />otherwise have under the Contract Documents or by
<br />Laws or Regulations in respect of any dispute.
<br />ARTICLE 17 - MISCELLANEOUS
<br />17.01 Giving Notice
<br />A. Whenever any provision of the Contract
<br />Documents requires the giving of written notice, it will
<br />be deemed to have been validly given if delivered in
<br />person to the individual or to a member of the firm or to
<br />an officer of the corporation for whom it is intended, or
<br />if delivered at or sent by registered or certified mail,
<br />postage prepaid, to the last business address known
<br />to the giver of the notice.
<br />17.02 Computation of Times
<br />A. When any period of time is referred to in the
<br />Contract Documents by days, it will be computed to
<br />exclude the first and include the last day of such period.
<br />If the last day of any such period falls on a Saturday or
<br />Sunday or on a day made a legal holiday by the law of
<br />the applicable jurisdiction, such day will be omitted
<br />from the computation.
<br />17.03 Cumulative Remedies
<br />A. The duties and obligations imposed by these
<br />General Conditions and the rights and remedies avail-
<br />able hereunder to the parties hereto are in addition to,
<br />and are not to be construed in any way as a limitation
<br />of, any rights and remedies available to any or all of
<br />them which are otherwise imposed or available by
<br />Laws or Regulations, by special warranty or guarantee,
<br />or by other provisions of the Contract Documents, and
<br />the provisions of this paragraph will be as effective as
<br />if repeated specifically in the Contract Documents in
<br />connection with each particular duty, obligation, right,
<br />and remedy to which they apply.
<br />17.04 Survival of Obligations
<br />A. All representations, indemnifications, warran-
<br />ties, and guarantees made in, required by, or given in
<br />accordance with the Contract Documents, as well as
<br />all continuing obligations indicated in the Contract
<br />General Conditions - 00700 - 37
<br />FAPublic Works\ENGINEERING DIVISION PROJECTS\1505-66th Ave Widening_49th St to 69th SAI-Admin\Bid Documents\Master Contract Documents\DIV 0_4_Conditions of the
<br />Contract.docx