TIME SCHEDULE <br />Task I Defiverahles� Draft Technical Memorandum 4 weeks fter° N'YP <br />Final'Technical Meinorandurn 2 w�eek,�., f"n..)m receipt of CoUntry' <br />Comrnents/RevieMeeting <br />Task 2 Deliverables: Draft'Fank Modification Plans -- 8 weeks after NI? <br />Final Tank Modification Plans- 2week.stromi-,e,ceiptcC(.)unty <br />Comments <br />"I ask :3 Deliverables: Draft Piping Modific-ation plans 8 weeks after NI? <br />Final Piping Modification Plans 2 weeks from receipt of County <br />CornnIODtS <br />Task 4 Deliverables: Permit Application I week frorn Final Piping Modification Plans <br />Task 5 Duration: Approximately, 3 Months <br />