A. CONTRACTOR has examined and carefully studied the Contract Documents and the other related
<br /> data identified in the Invitation to Bid documents.
<br /> B. CONTRACTOR has visited the Site and become familiar with and is satisfied as to the general,local,
<br /> and Site conditions that may affect cost,progress,and performance of the Work.
<br /> C. CONTRACTOR is familiar with and is satisfied as to all federal,state,and local Laws and Regulations
<br /> that may affect cost, progress,and performance of the Work.
<br /> D. CONTRACTOR has obtained and carefully studied (or assumes responsibility for having done so) all
<br /> additional or supplementary examinations, investigations, explorations, tests, studies, and data
<br /> concerning conditions(surface,subsurface,and Underground Facilities)at or contiguous to the Site
<br /> which may affect cost, progress, or performance of the Work or which relate to any aspect of the
<br /> means, methods, techniques, sequences, and procedures of construction to be employed by
<br /> CONTRACTOR, including applying the specific means, methods, techniques, sequences, and
<br /> procedures of construction, if any,expressly required by the Contract Documents to be employed
<br /> by CONTRACTOR,and safety precautions and programs incident thereto.
<br /> E. CONTRACTOR does not consider that any further examinations, investigations, explorations,tests,
<br /> studies, or data are necessary for the performance of the Work at the Contract Price, within the
<br /> Contract Times,and in accordance with the other terms and conditions of the Contract Documents.
<br /> F. CONTRACTOR is aware of the general nature of work to be performed by OWNER and others at the
<br /> Site that relates to the Work as indicated in the Contract Documents.
<br /> G. CONTRACTOR has correlated the information known to CONTRACTOR, information and
<br /> observations obtained from visits to the Site, reports and drawings identified in the Contract
<br /> Documents, and all additional examinations, investigations, explorations, tests, studies, and data
<br /> with the Contract Documents.
<br /> H. CONTRACTOR has given OWNER written notice of all conflicts,errors,ambiguities,or discrepancies
<br /> that CONTRACTOR has discovered in the Contract Documents, and the written resolution thereof
<br /> by OWNER is acceptable to CONTRACTOR.
<br /> I. The Contract Documents are generally sufficient to indicate and convey understanding of all terms
<br /> and conditions for performance and furnishing of the Work.
<br /> J. Contractor is registered with and will use the Department of Homeland Security's E-Verify system
<br /> (www.e-verify.gov) to confirm the employment eligibility of all newly hired employees for the
<br /> duration of this agreement,as required by Section 448.095,F.S.Contractor is also responsible for
<br /> obtaining proof of E-Verify registration and utilization for all subcontractors.
<br /> ARTICLE 8-CONTRACT DOCUMENTS
<br /> 8.01 Contents
<br /> A. The Contract Documents consist of the following:
<br />
|