Laserfiche WebLink
TIME SCHEDULE <br />Upon authorization to proceed by the COUNTY, final design documents are expected <br />to take approximately twelve (12) months from the Notice to Proceed (NTP). <br />NTP contingent upon BOCC approval <br />Preliminary Submittal (30% Design Drawings) 4 months following NTP <br />Constructability Submittal (60% Design Drawings) 7 months following NTP <br />Biddability Submittal (90% Design Drawings) 10 months following NTP <br />Permit Submittal 10 months following NTP <br />Production Submittal (100% Design Drawings) 12 months following NTP <br />(THE REMAINDER OF THIS PAGE IS INTENTIONALLY BLANK) <br />