Page 5 of 5 <br />Q: Is the County handing the initial (QC) testing? <br />A: No, it's on the Contractor to perform the required QC Testing. The County will perform <br />verification testing as needed. <br />Q: is there a design elevation? <br />A: No. <br />Q: What is the depth for the sheet piles? <br />A: The sheet pile depths and locations are to be determined by the Contractor based upon <br />their means and methods. The Contractor shall be responsible for procuring their own design <br />and submitting the proposed location to the County for approval as part of the submittal <br />process. <br />Q: Start date is dictated by FL City Gas? <br />A: Start date for construction will be dictated by the County and we are anticipating beginning <br />work around the middle of July since the bid opening doesn't occur until May Sth. It was noted <br />that once the award has been made that the Contractor aggressively pursue providing all <br />required submittals approved so that there are no hold ups with construction. <br />Jennifer Hyde: Change to Florida Statute requires the awarded contractor to be enrolled in the E - <br />Verify database. <br />10:32 A.M. meeting adjourned. <br />F:\Purchasing\Bids;2020-2021 FY (2021000)\2021045 4th Street Culvert at 90th AveAddendum 2\IR.C-2022_PREBID_M1N- <br />Final 20210421 (003).doc <br />