ARTICLE S - PAYMENT PROCEDURES
<br />5.01 Method of Payment
<br />Owner shall make payments to CONTRATOR, as properly invoiced after completion of work at each
<br />facility. Upon a determination of satisfactory completion, the COUNTY Project Manager will
<br />authorize payment to be made. All payments for services shall be made to the CONTRACTOR by the
<br />COUNTY in accordance with the Local Government Prompt Payment Act, as may be amended from
<br />time to time (Section 218.70, Florida Statutes, et seq.).
<br />5.02 Acceptance of Final Payment as Release
<br />The acceptance by the CONTRACTOR of final payment shall be and shall operate as a release to the
<br />OWNER from all claims and all liability to the CONTRACTOR other than claims in stated amounts as
<br />may be specifically excepted by the CONTRACTOR for all things done or furnished in connection with
<br />the work under this Agreement and for every act and neglect of the OWNER and others relating to
<br />or arising out of the work. Any payment, however, final or otherwise, shall not release the
<br />CONTRACTOR or its sureties from any obligations under this Agreement, the Invitation to Bid or the
<br />Public Construction Bond.
<br />ARTICLE 6 - INDEMNIFICATION
<br />6.01 CONTRACTOR shall indemnify and hold harmless the OWNER, and its officers and employees, from
<br />liabilities, damages, losses and costs, including, but not limited to, reasonable attorney's fees, to the
<br />extent caused by the negligence, recklessness, or intentional wrongful misconduct of the
<br />CONTRACTOR and persons employed or utilized by the CONTRACTOR in the performance of the
<br />Work.
<br />ARTICLE 7 - CONTRACTOR'S REPRESENTATIONS
<br />7.01 In order to induce OWNER to enter into this Agreement CONTRACTOR makes the following
<br />representations:
<br />A. CONTRACTOR has examined and carefully studied the Contract Documents and the other related
<br />data identified in the Invitation to Bid documents.
<br />B. CONTRACTOR has visited the Site and become familiar with and is satisfied as to the general, local,
<br />and Site conditions that may affect cost, progress, and performance of the Work.
<br />C. CONTRACTOR is familiar with and is satisfied as to all federal, state, and local Laws and Regulations
<br />that may affect cost, progress, and performance of the Work.
<br />D. CONTRACTOR has obtained and carefully studied (or assumes responsibility for having done so) all
<br />additional or supplementary examinations, investigations, explorations, tests, studies, and data
<br />concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the Site
<br />which may affect cost, progress, or performance of the Work or which relate to any aspect of the
<br />means, methods, techniques, sequences, and procedures of construction to be employed by
<br />CONTRACTOR, including applying the specific means, methods, techniques, sequences, and
<br />procedures of construction, if any, expressly required by the Contract Documents to be employed
<br />by CONTRACTOR, and safety precautions and programs incident thereto.