Laserfiche WebLink
4.03 Liquidated Damages <br />A. CONTRACTOR and OWNER recognize that time is of the essence of this Agreement and <br />that OWNER will suffer financial loss if the Work on the LWCF funded portion of the work is <br />not completed by April 30, 2022, plus any extensions thereof allowed in accordance with <br />Article 12 of the General Conditions. Liquidated damages will commence for this portion of <br />work. The parties also recognize the delays, expense, and difficulties involved in proving in <br />a legal proceeding the actual loss suffered by OWNER if the Work is not completed on time. <br />Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that <br />as liquidated damages for delay (but not as a penalty), CONTRACTOR shall pay OWNER <br />$1,197.00 for each calendar day that expires after April 30, 2022 for Substantial <br />Completion until the Work is substantially complete. After Substantial Completion, if <br />CONTRACTOR shall neglect, refuse, or fail to complete the remaining Work within the <br />Contract Time or any proper extension thereof granted by OWNER, CONTRACTOR shall <br />pay OWNER $1,197.00 for each calendar day that expires after the time specified in <br />paragraph 4.02 for completion and readiness for final payment until the Work is completed <br />and ready for final payment. <br />ARTICLE 5 - CONTRACT PRICE <br />5.01 OWNER shall pay CONTRACTOR for completion of the Work in accordance with the <br />Contract Documents, an amount in current funds equal to the sum of the amounts <br />determined pursuant to paragraph 5.01.A and summarized in paragraph 5.01.8, below: <br />A. For all Work, at the prices stated in CONTRACTOR's Bid, attached hereto as an exhibit. <br />B. THE CONTRACT SUM subject to additions and deductions provided in the Contract: <br />Numerical Amount: $912,614.90 <br />Written Amount: Nine -hundred twelve thousand six hundred fourteen dollars and <br />ninety cents. <br />ARTICLE 6 - PAYMENT PROCEDURES <br />6.01 Submittal and Processing of Payments <br />A. CONTRACTOR shall submit Applications for Payment in accordance with Article <br />14 of the General Conditions. Applications for Payment will be processed by <br />OWNER as provided in the General Conditions and the Contract Documents. <br />6.02 Progress Payments. <br />A. The OWNER shall make progress payments to the CONTRACTOR on the basis <br />of the approved partial payment request in accordance with the provisions of the <br />Local Government Prompt Payment Act, Florida Statutes section 218.70 et. seq. <br />The OWNER shall retain five percent (5%) of the payment amounts due to the <br />CONTRACTOR until final completion and acceptance of all work to be performed <br />by CONTRACTOR under the Contract Documents. <br />6.03 Pay Requests. <br />A. Each request for a progress payment shall be submitted on the application <br />provided by OWNER and the application for payment shall contain the <br />Section 00520 — Agreement for Public Works — Addendum 4 - 3 <br />