03,108/2022 <br />Sector 3 Phase 2 <br />Reach & Dune Restoration Project <br />Construction Update <br />• Phase 2 on -beach construction substantially complete as of <br />3/4/2022 <br />• Approx 2.9 mile stretch of beach from Wabasso Beach south to <br />Turtle trail beach park <br />• Estimated sand fill volume 280,000 cubic yards <br />• Estimated dune vegetation 302,820 native plan =a', Public Works Department <br />�v <br />• Coastal Engineering Division <br />7`fi — 16 <br />