14.03 CONTRACTOR's Warranty of Title <br />A. CONTRACTOR warrants and guarantees that <br />title to all Work, materials, and equipment covered by <br />any Application for Payment, whether incorporated in <br />the Project or not, will pass to OWNER no later than <br />the time of payment free and clear of all Liens. <br />14.04 Substantial Completion <br />A. When CONTRACTOR considers the entire <br />Work ready for its intended use CONTRACTOR shall <br />notify OWNER and ENGINEER in writing that the <br />entire Work is substantially complete (except for items <br />specifically listed by CONTRACTOR as incomplete) <br />and request that ENGINEER issue a certificate of <br />Substantial Completion. Promptly thereafter, <br />OWNER, CONTRACTOR, and ENGINEER shall <br />make an inspection of the Work to determine the status <br />of completion. If ENGINEER does not consider the <br />Work substantially complete, ENGINEER will notify <br />CONTRACTOR in writing giving the reasons therefore. <br />if ENGINEER a sudors the Week substantially n <br />mete GNIGIN EER will prepaFe nrl deliver +n OWN E <br />items to be sempleted OF serfested befefe final <br />payn ,^,t. OWNER shall have _. _eR day a#e . • + <br />sertiffeate-er attached -list. if, afteF GGRISideFing 66IGh <br />ebjeGtinns ENGINEER a nal 1A/ de that the k •s + <br />6ubGtan+iallr. <br />`nrnn18te, ENGINEER EER willwith•n 14 days- <br />ys- <br />aft.-t-91' 6;::_. GO6;•),^,Ref the ton+a+nrn sorfifiaate +n OWNICQ <br />theFefer. If, aner censideratiGR of /N ER's <br />nhioa+inns ENGINEER EER s ider the VVeFr ubstaa <br />+'ally nmmPlete ENGINEER ;eiill ..i+hin said 14 da,. <br />Gertifieate as ENGINEER believesjustified —ter <br />Gensideratien of aRY GbjeGtien6 frem OWNER. Atthe <br />f eMPI9+inn ENGINEER well deliver to OWNER and <br />divic;c^ of rEISPGRoibiiitievPcrndiRg fiRal paymeR <br />b8UVe9R OWNER .;;Pd- GGISITIR-A.CTOR With FeSpeGt t9 <br />mail iten'aa iiw, heat rtili+ieG iRSUFaRGe, andv.g.arra_nties <br />and g uaran+nns I Inloss OWNER aarl GONTRAGTOR <br />aim,.,agFee etherwise „, ..., , <br />WF wrier to €. __==R's issding the d f •+ <br />iVe <br />GertifiGate of Substantial r l + €PJGIN=ER's <br />B. OWNER shall have the right to exclude <br />CONTRACTOR from the Site after the date of <br />Substantial Completion, but OWNER shall allow CON- <br />TRACTOR reasonable access to complete or correct <br />items on the tentative list. <br />14.05 Partial Utilization <br />A. Use by OWNER at OWNER's option of any <br />substantially completed part of the Work which has <br />specifically been identified in the Contract Documents, <br />or which OWNER, ENGINEER, and CONTRACTOR <br />agree constitutes a separately functioning and usable <br />part of the Work that can be used by OWNER for its <br />intended purpose without significant interference with <br />CONTRACTOR's performance of the remainder of the <br />Work, may be accomplished prior to Substantial Com- <br />pletion of all the Work subject to the following condi- <br />tions. <br />1. OWNER at any time may request <br />CONTRACTOR in writing to permit OWNER to <br />use any such part of the Work which OWNER <br />believes to be ready for its intended use and <br />substantially complete. If CONTRACTOR <br />agrees that such part of the Work is <br />substantially complete, CONTRACTOR will <br />certify to OWNER and ENGINEER that such <br />part of the Work is substantially complete and <br />request ENGINEER to issue a certificate of <br />Substantial Completion for that part of the Work. <br />CONTRACTOR at any time may notify OWNER <br />and ENGINEER in writing that CONTRACTOR <br />considers any such part of the Work ready for its <br />intended use and substantially complete and <br />request ENGINEER to issue a certificate of <br />Substantial Completion for that part of the Work. <br />Within a reasonable time after either such <br />request, OWNER, CONTRACTOR, and <br />ENGINEER shall make an inspection of that <br />part of the Work to determine its status of <br />completion. If ENGINEER does not consider <br />that part of the Work to be substantially com- <br />plete, ENGINEER will notify OWNER and <br />CONTRACTOR in writing giving the reasons <br />therefor. If ENGINEER considers that part of <br />the Work to be substantially complete, the <br />provisions of paragraph 14.04 will apply with <br />respect to certification of Substantial Com- <br />pletion of that part of the Work and the division <br />of responsibility in respect thereof and access <br />thereto. <br />2. No occupancy or separate operation <br />of part of the Work may occur prior to <br />compliance with the requirements of paragraph <br />5.10 regarding property insurance. <br />14.06 Final Inspection <br />A. Upon written notice from CONTRACTOR that <br />the entire Work or an agreed portion thereof is <br />complete, ENGINEER will promptly make a final <br />General Conditions - 00700 - 34 <br />F:\PublicWorksNENGINEERING DIVISION PROJECTS\1639 69th Street 66th Avenue to US -1 Resurfacing (SCOP)\1-Admin\Bids\Bid Documents - Advertisement\DIV 0_2 -Conditions of the <br />Contract - 20211207.docx <br />