Work Order No. 55 <br />66t1 Avenue Phase II Utility <br />Adjustments <br />TIME SCHEDULE <br />Upon authorization to proceed by the COUNTY, final design documents are expected <br />to take approximately five (5) months from the Notice to Proceed (NTP). <br />NTP contingent upon BOCC approval <br />Constructability Submittal (60% Design Drawings) 2 months following NTP <br />Permit Submittal 3 months following NTP <br />Biddability Submittal (90% Design Drawings) 3 months following NTP <br />Production Submittal (100% Design Drawings) 4 months following NTP <br />(THE REMAINDER OF THIS PAGE IS INTENTIONALLY BLANK) <br />Page 5 of 6 129 <br />