ATKINS <br />Schedule <br />The anticipated schedule shown below is based on the weeks after the formal issuance of the <br />notice to proceed by County: <br />Task Duration from NTP <br />Project Kick -Off Meeting <br />2 weeks <br />Begin Survey Activities <br />6 weeks <br />Data Collection and Review <br />4 weeks <br />Draft Preliminary Design Report <br />12 weeks <br />Review Meeting <br />14 weeks <br />Final Preliminary Design Report <br />17 weeks <br />90% Design <br />26 weeks <br />Review Meeting <br />28 weeks <br />Final Design — Bid Documents <br />32 weeks <br />Bidding Support Services <br />TBD <br />23 <br />