ATKINS <br />Schedule <br />The anticipated schedule shown below is based on the weeks after the formal issuance of the <br />notice to proceed by County: <br />Task <br />Duration from NTP <br />Project Kick -Off Meeting and Site Visit 2 weeks <br />Begin Data Collection 2 weeks <br />Hydraulic Modeling Workshop 8 weeks <br />Pump Station Operations Workshop 10 weeks <br />Draft Preliminary Site Plan Virtual Meeting 12 weeks <br />Finalize Site Plan 16 weeks <br />