11TH DRIVE AND 37TH STREET ROADWAY AND INTERSECTION IMPROVEMENTS
<br />IRC PROJEcr No. 2001
<br />AACE Proposal No. P23-2555
<br />Page -3-
<br />ITEM #1: Field and Lab Testing of Roadway Construction
<br />• In -Place Density Testing of Roadway Embankment, Stabilized Subgrade and Base Course;
<br />- 85 tests @ $25.00/test (minimum 4 tests per hour, per trip) .........................................
<br />$2,125.00
<br />• In -Place Density Testing of Excavation Backfill for Removal of Old Storm Drainage;
<br />$4,250.00
<br />- 50 tests @ $25.00/test (minimum 4 tests per hour, per trip) .........................................
<br />$1,250.00
<br />• In -Place Density Testing of Storm Drainage Trench & Excavation Backfill;
<br />- 250 tests @ $25.00/test (minimum 4 tests per hour, per trip) ........................................
<br />$6,250.00
<br />• In -Place Density Testing of Misc. Deflections & Conflicts;
<br />$512.00
<br />- 25 tests @ $25.00/test (minimum 4 tests per hour, per trip) ...........................................
<br />$625.00
<br />• In -Place Density Testing of Sidewalk, Driveway, Bus Pad Subgrade;
<br />- 40 tests @ $25.00/test (minimum 4 tests per hour, per trip) .........................................
<br />$1,000.00
<br />• Moisture/Density Relationship (Proctor) Testing. 6 tests @ $91.00/test..................................
<br />$546.00
<br />• LBR Testing (Stabilized Subgrade, Base Rock); 5 tests @ $315.00/test.................................
<br />$1,575.00
<br />• Compressive Strength Testing of Concrete (Sidewalk., Curb, Bus Pad, Driveways, etc.)
<br />- 12 sets of concrete cylinders @ $95.00/set.......................................................
<br />$1,140.00
<br />• Engineering Technician (man-hours for sample collection, limited standby, etc.)
<br />$2,988.00
<br />- 100 hours @ $63.00/hour....................................................................
<br />$6,300.00
<br />Item #1 Subtotal: ...........................................
<br />$20,811.00
<br />ITEM #2: QC Services During Paving Operations
<br />• Asphalt Plant Inspection - Senior Transportation/Roadway Technician;
<br />- 2 Days x 10 hours/day @ $85.00/hr. x 1.5 (nighttime testing rate) ................................... $2,550.00
<br />- Asphalt Content and Extraction/Gradation Testing; 2 samples x $210.00/sample ........................ $420.00
<br />• Roadway Coring (2 Coring Events)
<br />- Engineering Technician (for Roadway Coring - 2 techs. required for all coring);
<br />2 events @ 8 hours/event x @ $63.00/hour x 2 technicians ........................................ $2,016.00
<br />- Coring Mobilization; 2 events x $100.00/mob..................................................... $200.00
<br />- Core Machine Usage; 2 days x $150.00/day....................................................... $300.00
<br />- Generator Usage; 2 days x $50.00/day............................................................ $100.00
<br />- Specific Gravity Testing (Unit Weight) of Cores; 8 cores x $37.00/core................................. $296.00
<br />• Snr. Project Engineer (Pre -Pave Mtg., Test Review, etc.); 10 hours x $128.00/hour....................... $1,280.00
<br />Item #2 Subtotal: ............................................ $7,162.00
<br />ITEM #3: Signalization Drilled Shaft and Anchor/Connection Bolt Inspections
<br />• Drilled Shaft Inspection and Testing.
<br />- Senior Transportation/Roadway Technician (drilled shaft (4) inspections, includes Pre -Con mtg.);
<br />50 hours @ $85.00/hour.......................................................................
<br />$4,250.00
<br />• Drilled Shaft Concrete Testing; 4 sets of concrete specimens @ $95.00/ set ..................................
<br />$380.00
<br />• Senior Field Technician (CTQP/FDOT Concrete Field Technician, if needed during pours);
<br />-24 hours @ $63.00/hour.......................................................................
<br />$1,512.00
<br />• Senior Project Engineer; 4 hours @ $128.00/hour.....................................................
<br />$512.00
<br />• Anchor/Connection Bolt Inspections:
<br />Since the contractor's proposed assembly methodology is currently unknown, we have assumed that
<br />separate technician -visits will be required for each of the four anchor assemblies, and also for each
<br />mast -arm connection (for a total of 8 technician -visits). Further, we have assumed that a bucket truck
<br />will be available for our use. Finally, we have budgeted limited standby time during this effort in the
<br />event that MOT requires adjusting, the bucket truck is delayed, etc. However, we have assumed that
<br />all inspections will occur during normal working hours/days (M -F, 7am-5pm).
<br />• Senior Field Technician (Bolted Connections): 6 visits x 6 hours/visit @ $83.00/hour ......................
<br />$2,988.00
<br />• Senior Project Engineer: 4 hours @ $128.00/hour.....................................................
<br />$512.00
<br />• Professional/Administrative Man-hours (Engineering Consultations, Reporting, etc.):
<br />- Senior Project Engineer; 3 hours @ $128.00/hr.......................................................
<br />$384.00
<br />- Technical Secretary; 5 hours @ $50.00/hr...........................................................
<br />2$ 50.00
<br />Item #3 Subtotal: ..................................
<br />$10,788.00