SECTION 00942 - Change Order Form <br />No. 1 <br />DATE OF ISSUANCE: 06/21/2023 EFFECTIVE DATE: 7/11/2023 <br />OWNER: Indian River County <br />CONTRACTOR Allen Concrete & Masonry, Inc. <br />Project:MOORHEN MARSH LOW ENERGY AQUATIC PLANT SYSTEM <br />OWNER's Project No. IRC -2107 OWNER'S Bid No. 2021038 <br />You are directed to make the following changes in the Contract Documents: <br />Description: <br />Change Order 1 for Part A of the Contract <br />Reason for Change Order: <br />The project is complete. This change order is to make final adjustment to bid line items, to <br />address plan omissions, and design changes for the construction of the Moorhen Marsh LEAPS <br />facility. This change order is to finalize Part A of the contract and release retainage to the <br />Contractor. Part B of the contract, that contains the one-year landscape maintenance and <br />warranty line items, will remain open as outlined in the bid documents. The following is a list of <br />plan errors, omissions and design changes for the construction of the Moorhen Marsh LEAPS <br />facility. This includes the following: <br />1. Front entrance modification needed as a result of the 53rd street widening (IRC -1505) — <br />$28,936.22 <br />2. Landscaping pay item discrepancies between the bill of materials and landscaping plans <br />- $26,654.25 <br />3. Construction of a sediment wall at the headworks structure that was omitted in the <br />structural plans — $16,015.71 <br />4. Installation of electrical service pull box required at the headworks structure for the 3- <br />phase service - $6,778.08 <br />5. Removal of a berm on the east side of the side of the property that was constructed after <br />the project survey was completed - $2,417.94 <br />6. Relocation of electrical conduit for the pole barn due to FPL service work — $1,857.37 <br />Attachments: <br />Description of Itemized Changes and Backup <br />CHANGE IN <br />CONTRACT PRICE: <br />Time <br />Description <br />Amount <br />Original Contract Price <br />$$10,987,684.90 <br />Net deeFeaee-of this <br />$$82,659.57 <br />Change Order: <br />(days) <br />Contract Price with all <br />$$11,070,344.47 <br />approved Change <br />(days) <br />Orders: <br />J I KAt- I UK pignature) <br />CHANGE IN CONTRACT TIMES <br />Description <br />Time <br />Original Contract Time: <br />(days) <br />Final Completion: <br />300 <br />Net increase this Change Order: <br />(days) <br />Final Completion: <br />317 <br />Contract Time with all approved <br />(days) <br />Change Orders: <br />Final Completion: <br />617 <br />Richard Reichenbach <br />Richard B. Szpyrka, P.E. <br />Public Works Director <br />Richard B. :aK^,roas=o,�PE.ma„ <br />Szpyrka <br />2ar,071213�31a.� <br />IRC -2107 CO#1 20230621 REDUCED <br />00942-1 <br />F:\Public Works\ENGINEERING DIVISION PROJECTS\2107 Moorhen Marsh LEAPS\1-Admin\Agenda Items\Change Orders\CO1 (PART A)\IRC-2107_CO#1_20230621 <br />REDUCED.doc Rev. 05/01 <br />