SECTION 00520 Agreement (Public Works) <br />THIS AGREEMENT is by and between INDIAN RIVER COUNTY, a Political Subdivision of the <br />State of Florida organized and existing under the Laws of the State of Florida, (hereinafter called <br />OWNER) and Prince Land, Inc. (hereinafter called CONTRACTOR). <br />OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree <br />as follows: <br />ARTICLE 1 -WORK <br />1.01 CONTRACTOR shall complete all Work as specified or indicated in the Contract <br />Documents. The Work is generally described as follows: <br />The proposed project includes a 12' wide millings walking trail, two driveway <br />connections to the adjacent roadways (43rd Avenue and Aviation Blvd.) a milling <br />access road connecting the two driveway aprons, resurfacing an existing parking <br />lot, and installing 60" pipe culvert. The County has stock piled millings on site for <br />the project. Contractor shall be required to crush stock piled millings to pass sieve <br />size of less than 1 inch. Also included in the project are installation of a new tree <br />line along the west side of the parcel (adjacent to 43rd Avenue) and constructing a <br />steel span/recyclable material pedestrian bridge connecting the walking trail parcel <br />to the cloverleaf fields to the east. <br />ARTICLE 2 - THE PROJECT <br />2.01 The Project for which the Work under the Contract Documents may be the whole or only a <br />part is generally described as follows: <br />Project Name: Jackie Robinson Training Complex Walking Trail <br />County Project Number: IRC -1908 <br />Bid Number: 2023041 <br />Project Address: 430326 th Street, Vero Beach, FL 32960 <br />ARTICLE 3 - ENGINEER <br />3.01 The Indian River County Public Works Department is hereinafter called the ENGINEER and <br />will act as OWNER's representative, assume all duties and responsibilities, and have the <br />rights and authority assigned to ENGINEER in the Contract Documents in connection with <br />the completion of the Work in accordance with the Contract Documents. <br />ARTICLE 4 - CONTRACT TIMES <br />4.01 Time of the Essence <br />A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness <br />for final payment as stated in the Contract Documents are of the essence of the Contract. <br />4.02 Days to Achieve Substantial Completion, Final Completion and Final Payment <br />Agreement (Public Works) REV 04-07 - 00520 - 2 <br />F:\Purchasing\Bids\2022-2023 FY (2023000)\2023041 ]RTC Walking Trail Rebid\SECTION 00520 Agreement.d— <br />