6.05 Acceptance of Final Payment as Release. <br />A. The acceptance by the CONTRACTOR of final payment shall be and shall operate <br />as a release to the OWNER from all claims and all liability to the CONTRACTOR <br />other than claims in stated amounts as may be specifically excepted by the <br />CONTRACTOR for all things done or furnished in connection with the work under <br />this Contract and for every act and neglect of the OWNER and others relating to <br />or arising out of the work. Any payment, however, final or otherwise, shall not <br />release the CONTRACTOR or its sureties from any obligations under the Contract <br />Documents or the Public Construction Bond. <br />ARTICLE 7 - INDEMNIFICATION <br />7.01 CONTRACTOR shall indemnify OWNER, ENGINEER, and others in accordance with <br />paragraph 6.20 (Indemnification) of the General Conditions to the Construction Contract. <br />ARTICLE 8 - CONTRACTOR'S REPRESENTATIONS <br />8.01 In order to induce OWNER to enter into this Agreement CONTRACTOR makes the <br />following representations: <br />A. CONTRACTOR has examined and carefully studied the Contract Documents and the other <br />related data identified in the Bidding Documents. <br />B. CONTRACTOR has visited the Site and become familiar with and is satisfied as to the <br />general, local, and Site conditions that may affect cost, progress, and performance of the <br />Work. <br />C. CONTRACTOR is familiar with and is satisfied as to all federal, state, and local Laws and <br />Regulations that may affect cost, progress, and performance of the Work. <br />D. CONTRACTOR has carefully studied all: (1) reports of explorations and tests of subsurface <br />conditions at or contiguous to the Site and all drawings of physical conditions in or relating <br />to existing surface or subsurface structures at or contiguous to the Site (except Underground <br />Facilities) which have been identified in the Supplementary Conditions as provided in <br />paragraph 4.02 of the General Conditions and (2) reports and drawings of a Hazardous <br />Environmental Condition, if any, at the Site which have been identified in the Supplementary <br />Conditions as provided in paragraph 4.06 of the General Conditions. <br />E. CONTRACTOR has obtained and carefully studied (or assumes responsibility for having <br />done so) all additional or supplementary examinations, investigations, explorations, tests, <br />studies, and data concerning conditions (surface, subsurface, and Underground Facilities) <br />at or contiguous to the Site which may affect cost, progress, or performance of the Work or <br />which relate to any aspect of the means, methods, techniques, sequences, and procedures <br />of construction to be employed by CONTRACTOR, including applying the specific means, <br />methods, techniques, sequences, and procedures of construction, if any, expressly required <br />Agreement (Public Works) REV 04-07 - 00520 - 5 <br />F:\Purchasing\Bids\2022-2023 FV (2023000(\2023059 Traffic Operations Facility\IRC-2104_Sample Agreement.docx <br />