Laserfiche WebLink
Schedule <br />The anticipated schedule shown below is based on the weeks after the formal issuance of the <br />signed Work Order and a Notice to Proceed (NTP) by the County. <br />Task <br />Project Kick -Off Meeting and Site Visit <br />Begin Data Collection and Review <br />Negotiate Walker Proposal <br />Draft RFP <br />Review by County <br />Final RFP <br />RFP Released by County <br />Award Recommendation <br />Task <br />Start of construction <br />Substantial completion <br />Letter of Concurrence <br />Duration from Engineering NTP <br />2 weeks <br />4 weeks <br />10 weeks <br />14 weeks <br />16 weeks <br />18 weeks <br />22 weeks <br />30 weeks <br />Duration from Construction NTP <br />12 weeks <br />42 weeks <br />52 weeks <br />