Laserfiche WebLink
f <br />3.4.1 a formal Written Amendment, <br />3.4.2 a Change Order (pursuant to paragraph 1(1.4}, or <br />3.4.3 a Work Directive Change (pursuant to paragraph I 1), <br />As indicated in paragraphs 11.2 and 12. 1, Contract Price and Contract Time may only be changed by <br />a Change, Order or a Written Amendment. <br />3,5 In addition, the requirements of the Contract Documents may be supplemented, and minor variations <br />and deviations in the Work may be authorized, in one or more of the following ways: <br />3.5.1 a field Order (pursuant to paragraph 9.5), <br />3.5.2 ENGINEER's review of a shop drawing or sample (pursuant to paragraphs 6.32 and 6.33), <br />or <br />3.5.3 ENGINEER's written interpretation or clarification (pursuant to paragraph 9.4). <br />Rcuse of Documents: <br />3.6 Neither CONTRACTOR nor any Subcontractor or Supplier or other person or organization <br />performing or furnishing any of the Work under a direct or indirect contract with OWNER shall have <br />or acquire any title to or ownership rights in any of the Drawings, Specifications or other docsnnents <br />(or copies of any thereof) prepared by or bearing the seal of ENGIN FFR; and they shalt not reuse any <br />of them on extensions of the Project or any other project without written consent of OWNER and <br />ENGINEER and specific written verification or adaptation by ENGINEER. <br />ARTICLE 4 - AVAILABILITY OF LANDS; PHYSICAL CONDITIONS; REFERENCE POINTS <br />Availability of Lands: <br />4.1 OWNER shall furnish, as indicated in the Contract Documents, the lands upon which the Work is to <br />be performed, rights-of-way and easements for access thereto, and such other lards which are <br />designated for the use of CONTRACTOR- Easements for permanent structures or permanent changes <br />in existing facilities will be obtained and paid for by OWNER, unless otherwise provided in the <br />Contract Documtrntts. If CONTRACTOR behoves that any delay in OWNER's furnishing these lands, <br />right -of --way or easements entitles CONTRACTOR to an extension of the Contract Time, <br />CONTRACTOR may make a claim therefor as provided in article 12. CONTRACTOR shall provide <br />for all additional lands and access thereto that may he required for temporary construction facilities <br />or storage of materials and equipment. <br />Physical Conditions/Available Reports:. <br />4.2 Exploration and Reports; Reference is made in the Supplementary Conditions for identification of <br />those reports of exploration and tests of subsurface conditions at the site that have been utilized by <br />ENGINEER in preparation of the Contract Documents. Such reports are not guaranteed as to <br />accuracy or completeness and are not part of the Contract Documents. <br />4.3 Unforeseen Conditions- CONTRACTOR shall promptly notify OWNER and ENGINEER it writing <br />of any subsurface or latent physical conditions at the site or in an existing structure differing mattenally <br />GFNERAL CONDITIONs , <br />GC - 6 <br />L., <br />