C-1 <br />Cl <br />Commencement of Contract Time, Notice to Proceed: <br />2.3 The Contract Time will commence to nun on the day indicated in the Notice to Proceed. A Notice <br />to Proceed maybe given at anytime after the effective date of the Agreement. In no event will the <br />Contract Time commence to run later titan the seventy-fifth (75) day after the day of Sid opening. <br />Starting the Project: <br />2.4 CONTRACTOR shall start to perform the Work on the date when the Contract Time commences <br />to run, but no Work shall be done at the site prior to the date on which the Contract Time <br />commences to run. <br />Before Starting Construction: <br />2.5 Before undertaking each part of the Work, CONTRACTOR shall carefully study and compare the <br />CONTRACT Documents and check and verify pertinent figures shown thereon and all applicable <br />field measurements. CONTRAC70R shall promptly report in writing to ENGINEER any conflict, <br />error or discrepancy which CONTRACTOR may discover and shall obtain a written interpretation <br />or clarification from ENGINEER before proceeding with any Work affected thereby; however, <br />CONTRACTOR shall not be liable to OWNER or ENGINEER for failure to report any conflict, <br />error or discrepancy in the Contract Documents, unless CONTRACTOR had actual knowledge <br />thereof or should reasonably have known thereof. <br />2.6 Within ten (10) days after the Effective Date of the Agreement (unless otherwise specified in the <br />General Requirements), CONTRACTOR shall submit to ENGINEER for review: <br />2.6.1 an estimated progress schedule indicating the starting and completion dates of the various <br />stages of the Work; <br />2.6.2 a preliminary schedule of Shop Drawing submissions; and <br />2.6.3 a preliminary schedule of values for all of the Work which will include quantities and prices <br />of items aggregating the Contract Price and will subdivide the Work into component parts <br />in sufficient detail to serve as the basis for progress payments during, constniction. Such <br />prices will include an appropriate amount of overhead and profit applicable to each item or <br />Work which will be confirmed in writing by CONTRACTOR at the time of submission. <br />2.7 Ten (10) days prior to any work commencing, CONTRACTOR shall deliver to OWNER, with a <br />copy to ENGINEER, certificates (and other evidence ofinsurance requested by OWNER) which <br />CONTRACTOR is required to purchase and maintain in accordance with Section 5. <br />!'reconstruction Conference: <br />2.8 Within twenty (20) days after the Effective Date of the Agreement, but before CONTRACTOR <br />starts the Work at the site, a contcrence attended by CONTRACTOR, ENGINEER and others as <br />appropriate will be held to discuss the schedules referred to in paragraph 2.6, to discuss procedures <br />for handling Shop Drawings and other submittals and tier processing Applications for Payment, and <br />to establish a working understanding aniong the parties as to the Work. <br />Finalizing Schedules: <br />2.9 Al less.It:n t!"Is d ys• t*e#i r: submi0on of thr first Apphealion I''m Payment a conference atlen;led <br />by CONTRACTOR, ENGINE -1 -ilk and others as appropriate will be held to finalize Lite SCkLt ulr:, <br />submitted in accordance with paragraph 2.6. The finialia.ed progress schedule will lie acceptable to <br />t;t M,RAL CONI11TIONS <br />rc - a <br />