<br />S CTION 01025
<br />MEASUP,EMENT AND PAYMENT
<br />PART 1 -
<br />GENERAL
<br />1.01
<br />GENERAL
<br />Measurement and payment will be based upon
<br />work completed
<br />and accepted in accordance with the Contract Documents..
<br />No separate payment will be made
<br />for excavation,
<br />trenching, dewatering, backfilling,
<br />leakage tests,
<br />surveying, density tests, or other incidental items of
<br />work not shown in the Agreement.
<br />1.02
<br />EQUIPMENT AND MATERIALS IN STORAGE
<br />Partial payment. for materials and equipment
<br />in proper
<br />storage at the site of the work or other
<br />approved storage
<br />site will be made for those items
<br />for which the
<br />Contractor has submitted paid invoices
<br />to the Engineer.
<br />The partial payment for stared materials will be 50% of
<br />the value of materials and equipment, based
<br />on receipted
<br />bills, furnished but not incorporated
<br />in the work, s
<br />determined by Engineer.
<br />1.03
<br />MEASUREMENT
<br />A. Mobilizations Measurement shall
<br />be on a lump sum
<br />basis, and shall be limited to the following
<br />maximum amounts:
<br />ORIGINAL CONTRACT AMOUNT MAXIMUM AMOUR
<br />FROM
<br />_
<br />MORE THAN TO AND -INCLUDING ,ITEM
<br />FOR MOBILIZATION
<br />0 100,000
<br />3,000
<br />100,000 500,000
<br />15,000
<br />500,000 1,000,000
<br />30,000
<br />1,000;000 2,000,000
<br />60,000
<br />2,000,000 3,000,000
<br />90 a 0'i+0
<br />3,000,000 4,000,000
<br />120,000
<br />4,000,000 5,000,000
<br />125,000
<br />5,000,000 6,000,000
<br />150,000
<br />6,000,000 7,000,000
<br />175,000
<br />7,000,000 10,000,000
<br />200,000
<br />10, 000, 000 ----•-------
<br />250,000