t {UGC01311.E1"iT) :aa <br />i; <br />SECTION 01311 <br />CONSTRUCTION SCHEDULES <br />PART 1 a GENERAL <br />1.01 REQUIREMENTS INCLUDED <br />A. Promptly after award of the Contract, Contractor <br />shall prepare and submit to the Engineer estimated <br />ated <br />construction progress for the Work, <br />subschedules of related activities which are <br />essential, to its progress. <br />B. Coordinate the work and scheduling with and around <br />other contractors and individual trades performing <br />work on the Project. <br />C. submit revised progress schedules with each <br />application for payment. <br />D. Progress schedule shall become part of Contract <br />Documents after approval by Engineer. <br />1.02 RELATED REQUIREMENTS <br />A. In other parts of the Contract Documents: <br />1. General Conditions: <br />a. Articles 2 and 6 Schedules, Reports, <br />and Records <br />b. Sections 6.1 and 6.2 - Supervision by <br />t Contractor <br />c. Article 15 - Supervision of Work, <br />Termination, and Delay <br />B. Specified in other sections: <br />y 1. Section 01000: Description of Work <br />2. Section 01201: Preconstruction Conference <br />3. Section 01340: Shop Drawings, <br />Product Data, <br />and SamplesI <br />r_ <br />1.03 FORM OF SCHEDULES <br />i <br />A. prepare schedules in the form. of « horizontal bar chart <br />as follows:. <br />01311-1 <br />L <br />