Laserfiche WebLink
Use of the Tree Mitigation Fund to complete this project is consistent with the intent of the <br />fund, and while an exact cost for the project will not be available until the RFP process is <br />complete, staff anticipates the cost of the project to be approximately $150,000 - $200,000. <br />If approved, a budget amendment will be brought before the Board to fund the <br />project from the Tree Mitigation Fund/Cash Forward -Oct 1St <br />SCHEDULE <br />It is anticipated that this project can be completed within 6-8 months of Board authorization. <br />RECOMMENDATION <br />Staff recommends that the Board of County Commissioners authorize Staff to develop a <br />scope and initiate the RFP process for the Gifford Customer Convenience Center <br />Landscaping Project. <br />ATTACHMENTS: <br />1. Aerial of Gifford Customer Convenience Center <br />17 <br />