<br />SECTION 01025
<br />MEASUREMENT AND PAYMENT
<br />PART I — GENERAL.
<br />1.01 GENERAL
<br />Measurement and payment will be based upon work completed and accepted in
<br />accordance with the Contract Documents. No separate payment will be made
<br />for excavation, trenching dewatering, backfilling, leakage tests, surveying,
<br />density tests, or other incidental items of work not shown in the Agreement.
<br />1.02 EQUIPMENT AND MATERIALS IN STORAGE
<br />Partial payment for materials and equipment in proper storage at the site of the
<br />work or other approved storage site will be made for those items for which the
<br />Contractor has submitted paid invoices to the Engineer. The partial payment
<br />for stored materials will be 50%oI'Ihe value of materials and equipment. based
<br />on receipted bills, furnished but not incorporated in the work, as determined by
<br />Engineer.
<br />1.03 MEASUREMENT
<br />A. Mobilixation: Measurement shall be on a lump sum basis, and shall be limited
<br />to the following maximum amounts:
<br />ORIGINAL CONTRACT AMOUNT (I MAXIMUM AMOUNT OP
<br />FROM MORE THAN TO AND INCLUDING ITEM POR MOBILIZATION
<br />0 100,000 3,000
<br />100,000 500,000 15,000
<br />500,000 1,000,000 30,000
<br />1,000,000 2,000,000 60,000
<br />2,000,000 3,000,000 90,000
<br />3,000,000 4,000,000 120,000
<br />4,000,000 5,000,000 125,000
<br />5,000,000 6,000,000 150,000
<br />6,000,000 7,000,000 175,000
<br />7,000,000 10,000,000 200,000
<br />10,000,000 --------- 250,000
<br />Should the lump sum price bid for the item Mobilization exceed the maximum
<br />permissible amount for this item, as specified herein, the bid price will be
<br />reduced to the maximum permissible amount, and the reduced price will be
<br />used in correctly determining the total price for comparison of bids received.