4.3 Information and data reflected in the Contract Documents with respect a <br />underground facilities at or contiguous to the site is based upon <br />information and date furnished to Owner and Engineer by owners of such <br />underground facilities or others, and Owner does not assume <br />responsibility for the accuracy or completeness thereof unless it is <br />expressly provided otherwise in the Supplementary Conditions. <br />4.4 Provisions conceming responsibilities for die adequacy of data furnished <br />to prospective Bidden on subsurface conditions, underground facilities <br />and other physical conditions, and possible changes in the Contract <br />Documents due to differing conditions appear in Paragraphs 4.2 and 4.3 of <br />the General Conditions. <br />4.5 Before submitting a Bid, each Bidder will, at Bidder's own expense, make <br />or obtain any additional examinations, investigations, explorations, tests, <br />and studies, and obtain any additional information and data which pertain <br />to the physical conditions (surface, subsurface and underground facilities) <br />at or contiguous to the site or otherwise which may affect cost, progress, <br />performance, or furnishing of the work and which Bidder deems necessary <br />to determine its Bid for perforating and furnishing the work in accordance <br />with the time, price and other terms and conditions of the Contract <br />Documents. <br />4.6 On request in advance, Owner will provide each Bidder access a the site <br />to conduct such explorations and tests as each Bidder deems necessary for <br />submission of a Bid. Bidder shall fill all holes, clean up, and restore the <br />site to its former condition upon completion of such explorations. <br />4.7 The lands upon which the work is to be performed, right-oRway and <br />easements for across thereto and other lands designed for use by the <br />Contractor in performing the work are identified in the Contract <br />Documents. All additional lands and access therete required for <br />temporary construction facilities or storage of materials and equipment are <br />to be provided by and paid for by the Contractor. Easements for <br />permanent structures or permanent changes in existing structures are to be <br />obtained and paid for by the Owner unless otherwise provided in the <br />Contract Documents. <br />001m).3 <br />r w+mcuuw .«.oim�.. <br />