Lump Sum Components <br /> Task Labor Fee <br /> 1) Permit Construction Plan Modifications $4,000 <br /> 2) Permit Modification Assistance $3,500 <br /> TOTAL $7,500 <br /> EXHIBIT C—TIME SCHEDULE <br /> Upon authorization to proceed by the COUNTY,final design documents are expected to take approximately <br /> sixty (60) days from the Notice to Proceed (NTP). <br /> NTP contingent upon BOCC approval <br /> Plans Preparation 30 days following NTP <br />